Roads & HighwaysIPM · Central Project +30.1% overrun#618749

Khammam-Devarapalle Pkg V [4L Access Controlled Greenfield from Gurvaygudem village to Devarapalle village Design Chainage 132664 to 162126

Ministry of Road Transport & HighwaysAndhra Pradesh
Revised Cost: ₹926 CrUtilization: 61.2%Overrun: +₹214 Cr

Original Cost

₹712 Cr

Baseline estimate

+30% overrun

Revised Cost

₹926 Cr

Latest approved cost

Expenditure

₹567 Cr

Spent to date

Utilization

61.2%

Of revised budget

Escalated

Cost Status

+30.1%

+₹214 Cr increase

Remaining

₹360 Cr

Budget left

Budget Utilization

61.2%
0%25%50%75%100%

Spent

₹567 Cr

Remaining

₹360 Cr

Total

₹926 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹712 Cr

Revised Cost

₹926 Cr

Increase

+₹214 Cr

Escalation

+30.1%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

25/09/2024

Revised Completion

31/07/2026

Completed

Project Details

Project Code618749
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateAndhra Pradesh
Data Month2026-06

Financial Summary

Original Cost₹712 Cr
Revised Cost₹926 Cr
Expenditure₹567 Cr
Original End Date25/09/2024
Revised Date31/07/2026

Project Intelligence

Cost has increased by ₹214 Cr (30.1%) from the original estimate of ₹712 Cr.

Expenditure stands at ₹567 Cr, which is 61.2% of the revised project cost.

Remaining budget: ₹360 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Khammam-Devarapalle Pkg V [4L Access Controlled Greenfield from Gurvaygudem village to Devarapalle village Design Chainage 132664 to 162126 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹712.00 Cr, later revised to ₹926.48 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Khammam-Devarapalle Pkg V [4L Access Controlled Greenfield from Gurvaygudem vill"?
Khammam-Devarapalle Pkg V [4L Access Controlled Greenfield from Gurvaygudem village to Devarapalle village Design Chainage 132664 to 162126 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Andhra Pradesh. Original cost: ₹712 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹712 Cr and has been revised to ₹926 Cr — a cost overrun of +30.1%. Expenditure to date: ₹567 Cr (61.2% of revised cost). Data as of 2026-06.
QWhich ministry is responsible for this project?
Khammam-Devarapalle Pkg V [4L Access Controlled Greenfield f is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618749. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Khammam-Devarapalle Pkg V [4L Access Controlled Greenfield f is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.