Original Cost
₹712 Cr
Baseline estimate
Revised Cost
₹926 Cr
Latest approved cost
Expenditure
₹423 Cr
Spent to date
Utilization
45.7%
Of revised budget
Cost Status
+30.1%
+₹214 Cr increase
Remaining
₹503 Cr
Budget left
Spent
₹423 Cr
Remaining
₹503 Cr
Total
₹926 Cr
Original Cost
₹712 Cr
Revised Cost
₹926 Cr
Increase
+₹214 Cr
Escalation
+30.1%
Project Approved
Construction / Implementation
Original End Date
25/09/2024
Revised Completion
30/06/2026
Completed
Cost has increased by ₹214 Cr (30.1%) from the original estimate of ₹712 Cr.
Expenditure stands at ₹423 Cr, which is 45.7% of the revised project cost.
Remaining budget: ₹503 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.