Original Cost
₹569 Cr
Baseline estimate
Revised Cost
₹752 Cr
Latest approved cost
Expenditure
₹356 Cr
Spent to date
Utilization
47.3%
Of revised budget
Cost Status
+32.2%
+₹183 Cr increase
Remaining
₹396 Cr
Budget left
Spent
₹356 Cr
Remaining
₹396 Cr
Total
₹752 Cr
Original Cost
₹569 Cr
Revised Cost
₹752 Cr
Increase
+₹183 Cr
Escalation
+32.2%
Project Approved
Construction / Implementation
Original End Date
25/09/2024
Revised Completion
31/05/2025
Completed
Cost has increased by ₹183 Cr (32.2%) from the original estimate of ₹569 Cr.
Expenditure stands at ₹356 Cr, which is 47.3% of the revised project cost.
Remaining budget: ₹396 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.