Original Cost
₹616 Cr
Baseline estimate
Revised Cost
₹982 Cr
Latest approved cost
Expenditure
₹432 Cr
Spent to date
Utilization
44.0%
Of revised budget
Cost Status
+59.4%
+₹366 Cr increase
Remaining
₹550 Cr
Budget left
Spent
₹432 Cr
Remaining
₹550 Cr
Total
₹982 Cr
Original Cost
₹616 Cr
Revised Cost
₹982 Cr
Increase
+₹366 Cr
Escalation
+59.4%
Project Approved
Construction / Implementation
Original End Date
12/09/2024
Revised Completion
30/06/2026
Completed
Cost has increased by ₹366 Cr (59.4%) from the original estimate of ₹616 Cr.
Expenditure stands at ₹432 Cr, which is 44.0% of the revised project cost.
Remaining budget: ₹550 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.