Original Cost
₹797 Cr
Baseline estimate
Revised Cost
₹1337 Cr
Latest approved cost
Expenditure
₹635 Cr
Spent to date
Utilization
47.5%
Of revised budget
Cost Status
+67.8%
+₹540 Cr increase
Remaining
₹702 Cr
Budget left
Spent
₹635 Cr
Remaining
₹702 Cr
Total
₹1337 Cr
Original Cost
₹797 Cr
Revised Cost
₹1337 Cr
Increase
+₹540 Cr
Escalation
+67.8%
Project Approved
Construction / Implementation
Original End Date
30/10/2024
Revised Completion
07/10/2026
Completed
Cost has increased by ₹540 Cr (67.8%) from the original estimate of ₹797 Cr.
Expenditure stands at ₹635 Cr, which is 47.5% of the revised project cost.
Remaining budget: ₹702 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.