Original Cost
₹1741 Cr
Baseline estimate
Revised Cost
₹2042 Cr
Latest approved cost
Expenditure
₹461 Cr
Spent to date
Utilization
22.6%
Of revised budget
Cost Status
+17.3%
+₹301 Cr increase
Remaining
₹1580 Cr
Budget left
Spent
₹461 Cr
Remaining
₹1580 Cr
Total
₹2042 Cr
Original Cost
₹1741 Cr
Revised Cost
₹2042 Cr
Increase
+₹301 Cr
Escalation
+17.3%
Project Approved
Construction / Implementation
Original End Date
30/08/2025
Revised Completion
31/10/2026
Completed
Cost has increased by ₹301 Cr (17.3%) from the original estimate of ₹1741 Cr.
Expenditure stands at ₹461 Cr, which is 22.6% of the revised project cost.
Remaining budget: ₹1580 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.