Roads & HighwaysIPM · Central Project#618899

Kallagam km.38.700 to Meensurutti Km.98.433 of NH-227 in Tamil Nadu

Ministry of Road Transport & HighwaysTamil Nadu
Revised Cost: ₹1499 CrUtilization: 74.2%

Original Cost

₹1499 Cr

Baseline estimate

On budget

Revised Cost

₹1499 Cr

Latest approved cost

Expenditure

₹1112 Cr

Spent to date

Utilization

74.2%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹387 Cr

Budget left

Budget Utilization

74.2%
0%25%50%75%100%

Spent

₹1112 Cr

Remaining

₹387 Cr

Total

₹1499 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

22/04/2021

Revised Completion

30/09/2026

Completed

Project Details

Project Code618899
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateTamil Nadu
Data Month2026-08

Financial Summary

Original Cost₹1499 Cr
Revised Cost₹1499 Cr
Expenditure₹1112 Cr
Original End Date22/04/2021
Revised Date30/09/2026

Project Intelligence

Project is within original budget of ₹1499 Cr — no cost escalation recorded.

Expenditure stands at ₹1112 Cr, which is 74.2% of the revised project cost.

Remaining budget: ₹387 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Kallagam km.38.700 to Meensurutti Km.98.433 of NH-227 in Tamil Nadu is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1499.00 Cr, later revised to ₹1499.12 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Kallagam km.38.700 to Meensurutti Km.98.433 of NH-227 in Tamil Nadu"?
Kallagam km.38.700 to Meensurutti Km.98.433 of NH-227 in Tamil Nadu is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Tamil Nadu. Original cost: ₹1499 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹1499 Cr has not been significantly revised. Expenditure: ₹1112 Cr (74.2% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Kallagam km.38.700 to Meensurutti Km.98.433 of NH-227 in Tam is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618899. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Kallagam km.38.700 to Meensurutti Km.98.433 of NH-227 in Tam is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.