Original Cost
₹751 Cr
Baseline estimate
Revised Cost
₹956 Cr
Latest approved cost
Expenditure
₹363 Cr
Spent to date
Utilization
38.0%
Of revised budget
Cost Status
+27.3%
+₹205 Cr increase
Remaining
₹592 Cr
Budget left
Spent
₹363 Cr
Remaining
₹592 Cr
Total
₹956 Cr
Original Cost
₹751 Cr
Revised Cost
₹956 Cr
Increase
+₹205 Cr
Escalation
+27.3%
Project Approved
Construction / Implementation
Original End Date
16/09/2019
Revised Completion
20/06/2026
Completed
Cost has increased by ₹205 Cr (27.3%) from the original estimate of ₹751 Cr.
Expenditure stands at ₹363 Cr, which is 38.0% of the revised project cost.
Remaining budget: ₹592 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.