Roads & HighwaysIPM · Central Project +27.3% overrun#619146

Kagvadar - Una Package-IV

Ministry of Road Transport & HighwaysGujarat
Revised Cost: ₹956 CrUtilization: 87.2%Overrun: +₹205 Cr

Original Cost

₹751 Cr

Baseline estimate

+27% overrun

Revised Cost

₹956 Cr

Latest approved cost

Expenditure

₹833 Cr

Spent to date

Utilization

87.2%

Of revised budget

Escalated

Cost Status

+27.3%

+₹205 Cr increase

Remaining

₹123 Cr

Budget left

Budget Utilization

87.2%
0%25%50%75%100%

Spent

₹833 Cr

Remaining

₹123 Cr

Total

₹956 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹751 Cr

Revised Cost

₹956 Cr

Increase

+₹205 Cr

Escalation

+27.3%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

16/09/2019

Revised Completion

31/07/2026

Completed

Project Details

Project Code619146
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateGujarat
Data Month2026-06

Financial Summary

Original Cost₹751 Cr
Revised Cost₹956 Cr
Expenditure₹833 Cr
Original End Date16/09/2019
Revised Date31/07/2026

Project Intelligence

Cost has increased by ₹205 Cr (27.3%) from the original estimate of ₹751 Cr.

Expenditure stands at ₹833 Cr, which is 87.2% of the revised project cost.

Remaining budget: ₹123 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Kagvadar - Una Package-IV is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹751.00 Cr, later revised to ₹955.78 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Kagvadar - Una Package-IV"?
Kagvadar - Una Package-IV is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Gujarat. Original cost: ₹751 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹751 Cr and has been revised to ₹956 Cr — a cost overrun of +27.3%. Expenditure to date: ₹833 Cr (87.2% of revised cost). Data as of 2026-06.
QWhich ministry is responsible for this project?
Kagvadar - Una Package-IV is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619146. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Kagvadar - Una Package-IV is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.