Kagvadar - Una Package-IV
Original Cost
₹751 Cr
Baseline estimate
Revised Cost
₹956 Cr
Latest approved cost
Expenditure
₹833 Cr
Spent to date
Utilization
87.2%
Of revised budget
Cost Status
+27.3%
+₹205 Cr increase
Remaining
₹123 Cr
Budget left
Budget Utilization
87.2%Spent
₹833 Cr
Remaining
₹123 Cr
Total
₹956 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹751 Cr
Revised Cost
₹956 Cr
Increase
+₹205 Cr
Escalation
+27.3%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
16/09/2019
Revised Completion
31/07/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹205 Cr (27.3%) from the original estimate of ₹751 Cr.
Expenditure stands at ₹833 Cr, which is 87.2% of the revised project cost.
Remaining budget: ₹123 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Kagvadar - Una Package-IV is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹751.00 Cr, later revised to ₹955.78 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Kagvadar - Una Package-IV"?
- Kagvadar - Una Package-IV is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Gujarat. Original cost: ₹751 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹751 Cr and has been revised to ₹956 Cr — a cost overrun of +27.3%. Expenditure to date: ₹833 Cr (87.2% of revised cost). Data as of 2026-06.
- QWhich ministry is responsible for this project?
- Kagvadar - Una Package-IV is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619146. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Kagvadar - Una Package-IV is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.