Original Cost
₹3636 Cr
Baseline estimate
Revised Cost
₹3526 Cr
Latest approved cost
Expenditure
₹596 Cr
Spent to date
Utilization
16.9%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹2931 Cr
Budget left
Spent
₹596 Cr
Remaining
₹2931 Cr
Total
₹3526 Cr
Project Approved
Construction / Implementation
Original End Date
18/01/2025
Revised Completion
31/05/2027
Completed
Project is within original budget of ₹3636 Cr — no cost escalation recorded.
Expenditure stands at ₹596 Cr, which is 16.9% of the revised project cost.
Remaining budget: ₹2931 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.