Roads & HighwaysIPM · Central Project +27.7% overrun#618007

Jaynagar-Narahia Section km 156.500 to km 219.945 Lot-III

Ministry of Road Transport & HighwaysBihar
Revised Cost: ₹706 CrUtilization: 0.0%Overrun: +₹153 Cr

Original Cost

₹553 Cr

Baseline estimate

+28% overrun

Revised Cost

₹706 Cr

Latest approved cost

Expenditure

₹0 Cr

Spent to date

Utilization

0.0%

Of revised budget

Escalated

Cost Status

+27.7%

+₹153 Cr increase

Remaining

₹706 Cr

Budget left

Budget Utilization

0.0%
0%25%50%75%100%

Spent

₹0 Cr

Remaining

₹706 Cr

Total

₹706 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹553 Cr

Revised Cost

₹706 Cr

Increase

+₹153 Cr

Escalation

+27.7%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

11/11/2018

Revised Completion

31/07/2026

Completed

Project Details

Project Code618007
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateBihar
Data Month2026-05

Financial Summary

Original Cost₹553 Cr
Revised Cost₹706 Cr
Expenditure₹0 Cr
Original End Date11/11/2018
Revised Date31/07/2026

Project Intelligence

Cost has increased by ₹153 Cr (27.7%) from the original estimate of ₹553 Cr.

Expenditure stands at ₹0 Cr, which is 0.0% of the revised project cost.

Remaining budget: ₹706 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Jaynagar-Narahia Section km 156.500 to km 219.945 Lot-III is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹553.00 Cr, later revised to ₹706.39 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Jaynagar-Narahia Section km 156.500 to km 219.945 Lot-III"?
Jaynagar-Narahia Section km 156.500 to km 219.945 Lot-III is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Bihar. Original cost: ₹553 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹553 Cr and has been revised to ₹706 Cr — a cost overrun of +27.7%. Expenditure to date: ₹0 Cr (N/A% of revised cost). Data as of 2026-05.
QWhich ministry is responsible for this project?
Jaynagar-Narahia Section km 156.500 to km 219.945 Lot-III is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618007. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Jaynagar-Narahia Section km 156.500 to km 219.945 Lot-III is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.