Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
BiharInfraTalesBIHARINFRATALES
DashboardTenderCensusMP FundCabinetEC MonitoringAirportsTownshipsLitigation
  1. BiharInfraTales
  2. /IPM Dashboard
  3. /Integrated Para Xylene [PX] and Purified Terephtha
Oil & GasIPM · Central Project#604859

Integrated Para Xylene [PX] and Purified Terephthalic Acid [PTA] Project at Paradip Refinery

Ministry of Petroleum & Natural GasOdishaData: 2026-05
Revised Cost: ₹11.8K CrUtilization: 599.5%

Original Cost

₹13.8K Cr

Baseline estimate

On Budget

Revised Cost

₹11.8K Cr

Latest approved cost

Expenditure

₹70.6K Cr

Spent to date

Utilization

599.5%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹0 Cr

Budget left

Budget Utilization

599.5%
0%25%50%75%100%

Spent

₹70.6K Cr

Remaining

₹0 Cr

Total

₹11.8K Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/01/2024

Revised Completion

31/08/2026

Completed

Project Details

Project Code604859
SectorOil & Gas
MinistryMinistry of Petroleum & Natural Gas
StateOdisha
Data Month2026-05

Financial & Timeline

Original Cost₹13.8K Cr
Revised Cost₹11.8K Cr
Expenditure₹70.6K Cr
Original End Date31/01/2024
Revised Date31/08/2026

Project Intelligence

Mega infrastructure project worth ₹11.8K Cr — among the largest central projects in Odisha.

Project is within original budget of ₹13.8K Cr — no cost escalation recorded.

Expenditure stands at ₹70.6K Cr, which is 599.5% of the revised project cost.

Remaining budget: ₹0 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.

Sector: Oil & Gas. Ministry: Ministry of Petroleum & Natural Gas.

Frequently Asked Questions

What is IPM project "Integrated Para Xylene [PX] and Purified Terephthalic Acid [PTA] Project at Para"?
Integrated Para Xylene [PX] and Purified Terephthalic Acid [PTA] Project at Paradip Refinery is a centrally-funded infrastructure project under the Ministry of Petroleum & Natural Gas, tracked through the Investment Project Monitoring (IPM) system. Sector: Oil & Gas. State: Odisha. Original cost: ₹13805 Cr.
What is the cost overrun for this Bihar IPM project?
The original cost was ₹13805 Cr and has been revised to ₹11783 Cr — a cost overrun of -14.6%. Expenditure to date: ₹70637 Cr (599.5% of revised cost). Data as of 2026-05.
Which ministry is responsible for this project?
Integrated Para Xylene [PX] and Purified Terephthalic Acid [ is under the Ministry of Petroleum & Natural Gas in the Oil & Gas sector. Project code: 604859. Bihar is one of the states tracked under the central IPM dashboard for this project.
What is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Integrated Para Xylene [PX] and Purified Terephthalic Acid [ is one of several Bihar projects tracked under the Oil & Gas sector on the IPM system.

Related Resources

IPM

IPM Central Project Dashboard

All central infrastructure projects in Bihar

Projects

Bihar State Projects

State-funded infrastructure project tracker

NHAI

NHAI Drone Tracker

Real-time NHAI highway construction monitoring

Railway

Bihar Railway Projects

Railway infrastructure project tracker

RCD

Bihar RCD PMIS

State road and bridge project tracker

Tenders

Bihar Government Tenders

Procurement notices for infrastructure projects

Cabinet

Bihar Cabinet Decisions

Policy approvals for infrastructure

EC

EC & Forest Clearances

Environmental clearances for Bihar projects

Upcoming

Upcoming Bihar Projects

Infrastructure pipeline and future projects

Districts

Bihar District Data

District demographics and infrastructure overview