Original Cost
₹328 Cr
Baseline estimate
Revised Cost
₹344 Cr
Latest approved cost
Expenditure
₹218 Cr
Spent to date
Utilization
63.3%
Of revised budget
Cost Status
+5.0%
+₹16 Cr increase
Remaining
₹126 Cr
Budget left
Spent
₹218 Cr
Remaining
₹126 Cr
Total
₹344 Cr
Original Cost
₹328 Cr
Revised Cost
₹344 Cr
Increase
+₹16 Cr
Escalation
+5.0%
Project Approved
Construction / Implementation
Original End Date
08/08/2025
Revised Completion
31/12/2026
Completed
Cost has increased by ₹16 Cr (5.0%) from the original estimate of ₹328 Cr.
Expenditure stands at ₹218 Cr, which is 63.3% of the revised project cost.
Remaining budget: ₹126 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Oil & Gas. Ministry: Ministry of Petroleum & Natural Gas.