Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
BiharInfraTalesBIHARINFRATALES
DashboardTenderCensusMP FundCabinetEC MonitoringAirportsTownshipsLitigation
  1. BiharInfraTales
  2. /IPM Dashboard
  3. /Installation of Independent De- Aromatized Solvent
Oil & GasIPM · Central Project#709789

Installation of Independent De- Aromatized Solvents [DAS] production facilities at MR

Ministry of Petroleum & Natural GasMaharashtraData: 2026-01
Revised Cost: ₹343 CrUtilization: 73.0%

Original Cost

₹405 Cr

Baseline estimate

On Budget

Revised Cost

₹343 Cr

Latest approved cost

Expenditure

₹250 Cr

Spent to date

Utilization

73.0%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹93 Cr

Budget left

Budget Utilization

73.0%
0%25%50%75%100%

Spent

₹250 Cr

Remaining

₹93 Cr

Total

₹343 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/07/2025

Revised Completion

20/02/2026

Completed

Project Details

Project Code709789
SectorOil & Gas
MinistryMinistry of Petroleum & Natural Gas
StateMaharashtra
Data Month2026-01

Financial & Timeline

Original Cost₹405 Cr
Revised Cost₹343 Cr
Expenditure₹250 Cr
Original End Date31/07/2025
Revised Date20/02/2026

Project Intelligence

Project is within original budget of ₹405 Cr — no cost escalation recorded.

Expenditure stands at ₹250 Cr, which is 73.0% of the revised project cost.

Remaining budget: ₹93 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.

Sector: Oil & Gas. Ministry: Ministry of Petroleum & Natural Gas.

Frequently Asked Questions

What is IPM project "Installation of Independent De- Aromatized Solvents [DAS] production facilities "?
Installation of Independent De- Aromatized Solvents [DAS] production facilities at MR is a centrally-funded infrastructure project under the Ministry of Petroleum & Natural Gas, tracked through the Investment Project Monitoring (IPM) system. Sector: Oil & Gas. State: Maharashtra. Original cost: ₹405 Cr.
What is the cost overrun for this Bihar IPM project?
The original cost was ₹405 Cr and has been revised to ₹343 Cr — a cost overrun of -15.3%. Expenditure to date: ₹250 Cr (73.0% of revised cost). Data as of 2026-01.
Which ministry is responsible for this project?
Installation of Independent De- Aromatized Solvents [DAS] pr is under the Ministry of Petroleum & Natural Gas in the Oil & Gas sector. Project code: 709789. Bihar is one of the states tracked under the central IPM dashboard for this project.
What is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Installation of Independent De- Aromatized Solvents [DAS] pr is one of several Bihar projects tracked under the Oil & Gas sector on the IPM system.

Related Resources

IPM

IPM Central Project Dashboard

All central infrastructure projects in Bihar

Projects

Bihar State Projects

State-funded infrastructure project tracker

NHAI

NHAI Drone Tracker

Real-time NHAI highway construction monitoring

Railway

Bihar Railway Projects

Railway infrastructure project tracker

RCD

Bihar RCD PMIS

State road and bridge project tracker

Tenders

Bihar Government Tenders

Procurement notices for infrastructure projects

Cabinet

Bihar Cabinet Decisions

Policy approvals for infrastructure

EC

EC & Forest Clearances

Environmental clearances for Bihar projects

Upcoming

Upcoming Bihar Projects

Infrastructure pipeline and future projects

Districts

Bihar District Data

District demographics and infrastructure overview