Oil & GasIPM · Central Project +5.5% overrun#709777

Installation of Bitumen Manufacturing Unit along with allied facilities at Barauni Refinery

Ministry of Petroleum & Natural GasBihar
Revised Cost: ₹410 CrUtilization: 31.3%Overrun: +₹21 Cr

Original Cost

₹389 Cr

Baseline estimate

+6% overrun

Revised Cost

₹410 Cr

Latest approved cost

Expenditure

₹128 Cr

Spent to date

Utilization

31.3%

Of revised budget

Escalated

Cost Status

+5.5%

+₹21 Cr increase

Remaining

₹282 Cr

Budget left

Budget Utilization

31.3%
0%25%50%75%100%

Spent

₹128 Cr

Remaining

₹282 Cr

Total

₹410 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹389 Cr

Revised Cost

₹410 Cr

Increase

+₹21 Cr

Escalation

+5.5%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

30/04/2025

Revised Completion

30/06/2027

Completed

Project Details

Project Code709777
SectorOil & Gas
MinistryMinistry of Petroleum & Natural Gas
StateBihar
Data Month2026-08

Financial Summary

Original Cost₹389 Cr
Revised Cost₹410 Cr
Expenditure₹128 Cr
Original End Date30/04/2025
Revised Date30/06/2027

Project Intelligence

Cost has increased by ₹21 Cr (5.5%) from the original estimate of ₹389 Cr.

Expenditure stands at ₹128 Cr, which is 31.3% of the revised project cost.

Remaining budget: ₹282 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Oil & Gas. Ministry: Ministry of Petroleum & Natural Gas.

Installation of Bitumen Manufacturing Unit along with allied facilities at Barauni Refinery is a centrally-funded infrastructure project under Ministry of Petroleum & Natural Gas, in the Oil & Gas sector. The original approved cost is ₹389.00 Cr, later revised to ₹410.30 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Installation of Bitumen Manufacturing Unit along with allied facilities at Barau"?
Installation of Bitumen Manufacturing Unit along with allied facilities at Barauni Refinery is a centrally-funded infrastructure project under the Ministry of Petroleum & Natural Gas, tracked through the Investment Project Monitoring (IPM) system. Sector: Oil & Gas. State: Bihar. Original cost: ₹389 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹389 Cr and has been revised to ₹410 Cr — a cost overrun of +5.5%. Expenditure to date: ₹128 Cr (31.3% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Installation of Bitumen Manufacturing Unit along with allied is under the Ministry of Petroleum & Natural Gas in the Oil & Gas sector. Project code: 709777. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Installation of Bitumen Manufacturing Unit along with allied is one of several Bihar projects tracked under the Oil & Gas sector on the IPM system.