allied facilities at Barauni Refinery
Original Cost
₹389 Cr
Baseline estimate
Revised Cost
₹340 Cr
Latest approved cost
Expenditure
₹116 Cr
Spent to date
Utilization
34.0%
Of revised cost
Cost Overrun
On Budget
No escalation
Remaining
₹224 Cr
Budget left
Spent
₹116 Cr
Remaining
₹224 Cr
Total
₹340 Cr
34.0%
Utilized
Project Approved
Construction / Implementation
Original End Date
2025-04-30
Revised Completion
2027-01-31
Completed
Project is within original budget of ₹389 Cr — no cost escalation recorded.
Expenditure stands at ₹116 Cr, which is 34.0% of the revised project cost.
Remaining budget: ₹224 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Oil & Gas. Ministry: Ministry of Petroleum & Natural Gas.