Original Cost
₹1146 Cr
Baseline estimate
Revised Cost
₹1241 Cr
Latest approved cost
Expenditure
₹626 Cr
Spent to date
Utilization
50.5%
Of revised budget
Cost Status
+8.3%
+₹95 Cr increase
Remaining
₹615 Cr
Budget left
Budget Utilization
50.5%Spent
₹626 Cr
Remaining
₹615 Cr
Total
₹1241 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹1146 Cr
Revised Cost
₹1241 Cr
Increase
+₹95 Cr
Escalation
+8.3%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
06/10/2023
Revised Completion
15/06/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹95 Cr (8.3%) from the original estimate of ₹1146 Cr.
Expenditure stands at ₹626 Cr, which is 50.5% of the revised project cost.
Remaining budget: ₹615 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Indore - Harda Pkg-III [Nanasa to Pidgaon Section from km 95.000 to km 142.445] is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1146.00 Cr, later revised to ₹1240.64 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Indore - Harda Pkg-III [Nanasa to Pidgaon Section from km 95.000 to km 142.445]"?
- Indore - Harda Pkg-III [Nanasa to Pidgaon Section from km 95.000 to km 142.445] is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Madhya Pradesh. Original cost: ₹1146 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1146 Cr and has been revised to ₹1241 Cr — a cost overrun of +8.3%. Expenditure to date: ₹626 Cr (50.5% of revised cost). Data as of 2026-05.
- QWhich ministry is responsible for this project?
- Indore - Harda Pkg-III [Nanasa to Pidgaon Section from km 95 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618695. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Indore - Harda Pkg-III [Nanasa to Pidgaon Section from km 95 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.