Original Cost
₹1146 Cr
Baseline estimate
Revised Cost
₹1241 Cr
Latest approved cost
Expenditure
₹626 Cr
Spent to date
Utilization
50.5%
Of revised budget
Cost Status
+8.3%
+₹95 Cr increase
Remaining
₹615 Cr
Budget left
Spent
₹626 Cr
Remaining
₹615 Cr
Total
₹1241 Cr
Original Cost
₹1146 Cr
Revised Cost
₹1241 Cr
Increase
+₹95 Cr
Escalation
+8.3%
Project Approved
Construction / Implementation
Original End Date
06/10/2023
Revised Completion
15/06/2026
Completed
Cost has increased by ₹95 Cr (8.3%) from the original estimate of ₹1146 Cr.
Expenditure stands at ₹626 Cr, which is 50.5% of the revised project cost.
Remaining budget: ₹615 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.