Original Cost
₹1082 Cr
Baseline estimate
Revised Cost
₹1147 Cr
Latest approved cost
Expenditure
₹369 Cr
Spent to date
Utilization
32.2%
Of revised budget
Cost Status
+6.0%
+₹65 Cr increase
Remaining
₹778 Cr
Budget left
Spent
₹369 Cr
Remaining
₹778 Cr
Total
₹1147 Cr
Original Cost
₹1082 Cr
Revised Cost
₹1147 Cr
Increase
+₹65 Cr
Escalation
+6.0%
Project Approved
Construction / Implementation
Original End Date
14/03/2026
Revised Completion
20/11/2027
Completed
Cost has increased by ₹65 Cr (6.0%) from the original estimate of ₹1082 Cr.
Expenditure stands at ₹369 Cr, which is 32.2% of the revised project cost.
Remaining budget: ₹778 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.