Original Cost
₹1163 Cr
Baseline estimate
Revised Cost
₹1531 Cr
Latest approved cost
Expenditure
₹547 Cr
Spent to date
Utilization
35.7%
Of revised budget
Cost Status
+31.6%
+₹368 Cr increase
Remaining
₹984 Cr
Budget left
Spent
₹547 Cr
Remaining
₹984 Cr
Total
₹1531 Cr
Original Cost
₹1163 Cr
Revised Cost
₹1531 Cr
Increase
+₹368 Cr
Escalation
+31.6%
Project Approved
Construction / Implementation
Original End Date
15/01/2025
Revised Completion
31/10/2026
Completed
Cost has increased by ₹368 Cr (31.6%) from the original estimate of ₹1163 Cr.
Expenditure stands at ₹547 Cr, which is 35.7% of the revised project cost.
Remaining budget: ₹984 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.