Indore - Edlabad Pkg-II [Tejajinagar to Balwara]
Original Cost
₹1163 Cr
Baseline estimate
Revised Cost
₹1531 Cr
Latest approved cost
Expenditure
₹825 Cr
Spent to date
Utilization
53.9%
Of revised budget
Cost Status
+31.6%
+₹368 Cr increase
Remaining
₹706 Cr
Budget left
Budget Utilization
53.9%Spent
₹825 Cr
Remaining
₹706 Cr
Total
₹1531 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹1163 Cr
Revised Cost
₹1531 Cr
Increase
+₹368 Cr
Escalation
+31.6%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
15/01/2025
Revised Completion
31/12/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹368 Cr (31.6%) from the original estimate of ₹1163 Cr.
Expenditure stands at ₹825 Cr, which is 53.9% of the revised project cost.
Remaining budget: ₹706 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Indore - Edlabad Pkg-II [Tejajinagar to Balwara] is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1163.00 Cr, later revised to ₹1530.82 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Indore - Edlabad Pkg-II [Tejajinagar to Balwara]"?
- Indore - Edlabad Pkg-II [Tejajinagar to Balwara] is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Madhya Pradesh. Original cost: ₹1163 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1163 Cr and has been revised to ₹1531 Cr — a cost overrun of +31.6%. Expenditure to date: ₹825 Cr (53.9% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Indore - Edlabad Pkg-II [Tejajinagar to Balwara] is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618621. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Indore - Edlabad Pkg-II [Tejajinagar to Balwara] is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.