Roads & HighwaysIPM · Central Project#618377

Improvement/Widening to 2-L with Paved Shoulder/4-L from Km 81740 to Km 93490 design Km 0000 to Km 10670 of NH-40 New NH-106 & 206 section & 4-L from design Km 0.00 to Km 0.930 of NH-44 section between Shillong-Dawki under JICA ODA Loan assistance Phase-II -Balance Work Pkg-1

Ministry of Road Transport & HighwaysMeghalaya
Revised Cost: ₹351 CrUtilization: 69.4%

Original Cost

₹351 Cr

Baseline estimate

On budget

Revised Cost

₹351 Cr

Latest approved cost

Expenditure

₹244 Cr

Spent to date

Utilization

69.4%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹108 Cr

Budget left

Budget Utilization

69.4%
0%25%50%75%100%

Spent

₹244 Cr

Remaining

₹108 Cr

Total

₹351 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

22/10/2025

Revised Completion

15/06/2026

Completed

Project Details

Project Code618377
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateMeghalaya
Data Month2026-08

Financial Summary

Original Cost₹351 Cr
Revised Cost₹351 Cr
Expenditure₹244 Cr
Original End Date22/10/2025
Revised Date15/06/2026

Project Intelligence

Project is within original budget of ₹351 Cr — no cost escalation recorded.

Expenditure stands at ₹244 Cr, which is 69.4% of the revised project cost.

Remaining budget: ₹108 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Improvement/Widening to 2-L with Paved Shoulder/4-L from Km 81740 to Km 93490 design Km 0000 to Km 10670 of NH-40 New NH-106 & 206 section & 4-L from design Km 0.00 to Km 0.930 of NH-44 section between Shillong-Dawki under JICA ODA Loan assistance Phase-II -Balance Work Pkg-1 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹351.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Improvement/Widening to 2-L with Paved Shoulder/4-L from Km 81740 to Km 93490 de"?
Improvement/Widening to 2-L with Paved Shoulder/4-L from Km 81740 to Km 93490 design Km 0000 to Km 10670 of NH-40 New NH-106 & 206 section & 4-L from design Km 0.00 to Km 0.930 of NH-44 section between Shillong-Dawki under JICA ODA Loan assistance Phase-II -Balance Work Pkg-1 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Meghalaya. Original cost: ₹351 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹351 Cr has not been significantly revised. Expenditure: ₹244 Cr (69.4% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Improvement/Widening to 2-L with Paved Shoulder/4-L from Km is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618377. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Improvement/Widening to 2-L with Paved Shoulder/4-L from Km is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.