Improvement/Widening to 2-L with Paved Shoulder/ 4-Laning of NH-40 section from Km 151330 to Km 163400 design Km 63.530 to Km 71.520 including Dawki Bridge of length 368 m between Shillong-Dawki under JICA ODA Loan assistance Phase-II Pkg-5 -Balance work
Original Cost
₹284 Cr
Baseline estimate
Revised Cost
₹284 Cr
Latest approved cost
Expenditure
₹171 Cr
Spent to date
Utilization
60.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹113 Cr
Budget left
Budget Utilization
60.1%Spent
₹171 Cr
Remaining
₹113 Cr
Total
₹284 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
13/11/2026
Revised Completion
13/11/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹284 Cr — no cost escalation recorded.
Expenditure stands at ₹171 Cr, which is 60.1% of the revised project cost.
Remaining budget: ₹113 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Improvement/Widening to 2-L with Paved Shoulder/ 4-Laning of NH-40 section from Km 151330 to Km 163400 design Km 63.530 to Km 71.520 including Dawki Bridge of length 368 m between Shillong-Dawki under JICA ODA Loan assistance Phase-II Pkg-5 -Balance work is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹284.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Improvement/Widening to 2-L with Paved Shoulder/ 4-Laning of NH-40 section from "?
- Improvement/Widening to 2-L with Paved Shoulder/ 4-Laning of NH-40 section from Km 151330 to Km 163400 design Km 63.530 to Km 71.520 including Dawki Bridge of length 368 m between Shillong-Dawki under JICA ODA Loan assistance Phase-II Pkg-5 -Balance work is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Meghalaya. Original cost: ₹284 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹284 Cr has not been significantly revised. Expenditure: ₹171 Cr (60.1% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Improvement/Widening to 2-L with Paved Shoulder/ 4-Laning of is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618374. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Improvement/Widening to 2-L with Paved Shoulder/ 4-Laning of is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.