Improvement/construction of 2-lane with paved shoulder of Askote Llipulekh road from Tawaghat village to Budhi village design km. 56935 to km 95748 and from end of Tunnel portal to Kali Mandir design km 113828 to km. 133078 [total design length 58.063 km] under project Hirak of BRO in the state of Uttarakhand under Bharatmala Pariyojna on EPC Mode
Original Cost
₹650 Cr
Baseline estimate
Revised Cost
₹650 Cr
Latest approved cost
Expenditure
₹97 Cr
Spent to date
Utilization
15.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹553 Cr
Budget left
Budget Utilization
15.0%Spent
₹97 Cr
Remaining
₹553 Cr
Total
₹650 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
24/11/2026
Revised Completion
12/07/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹650 Cr — no cost escalation recorded.
Expenditure stands at ₹97 Cr, which is 15.0% of the revised project cost.
Remaining budget: ₹553 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Improvement/construction of 2-lane with paved shoulder of Askote Llipulekh road from Tawaghat village to Budhi village design km. 56935 to km 95748 and from end of Tunnel portal to Kali Mandir design km 113828 to km. 133078 [total design length 58.063 km] under project Hirak of BRO in the state of Uttarakhand under Bharatmala Pariyojna on EPC Mode is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹650.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Improvement/construction of 2-lane with paved shoulder of Askote Llipulekh road "?
- Improvement/construction of 2-lane with paved shoulder of Askote Llipulekh road from Tawaghat village to Budhi village design km. 56935 to km 95748 and from end of Tunnel portal to Kali Mandir design km 113828 to km. 133078 [total design length 58.063 km] under project Hirak of BRO in the state of Uttarakhand under Bharatmala Pariyojna on EPC Mode is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttarakhand. Original cost: ₹650 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹650 Cr has not been significantly revised. Expenditure: ₹97 Cr (15.0% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Improvement/construction of 2-lane with paved shoulder of As is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618211. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Improvement/construction of 2-lane with paved shoulder of As is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.