Improvement & Up-gradation of NH-734 Section of Moradabad-Thakurdwara Kashipur including Moradabad & Kashipur Bypasse Package-III Kashipur Bypass Length 14.490 Km., Starts from Ch. 38770 and ends at Ch. 53260 existing Ch. 05560
Original Cost
₹936 Cr
Baseline estimate
Revised Cost
₹718 Cr
Latest approved cost
Expenditure
₹400 Cr
Spent to date
Utilization
55.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹317 Cr
Budget left
Budget Utilization
55.8%Spent
₹400 Cr
Remaining
₹317 Cr
Total
₹718 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
14/09/2025
Revised Completion
31/03/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹936 Cr — no cost escalation recorded.
Expenditure stands at ₹400 Cr, which is 55.8% of the revised project cost.
Remaining budget: ₹317 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Improvement & Up-gradation of NH-734 Section of Moradabad-Thakurdwara Kashipur including Moradabad & Kashipur Bypasse Package-III Kashipur Bypass Length 14.490 Km., Starts from Ch. 38770 and ends at Ch. 53260 existing Ch. 05560 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹936.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Improvement & Up-gradation of NH-734 Section of Moradabad-Thakurdwara Kashipur i"?
- Improvement & Up-gradation of NH-734 Section of Moradabad-Thakurdwara Kashipur including Moradabad & Kashipur Bypasse Package-III Kashipur Bypass Length 14.490 Km., Starts from Ch. 38770 and ends at Ch. 53260 existing Ch. 05560 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttarakhand. Original cost: ₹936 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹936 Cr and has been revised to ₹718 Cr — a cost overrun of -23.3%. Expenditure to date: ₹400 Cr (55.8% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Improvement & Up-gradation of NH-734 Section of Moradabad-Th is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618928. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Improvement & Up-gradation of NH-734 Section of Moradabad-Th is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.