Original Cost
₹686 Cr
Baseline estimate
Revised Cost
₹680 Cr
Latest approved cost
Expenditure
₹466 Cr
Spent to date
Utilization
68.6%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹214 Cr
Budget left
Spent
₹466 Cr
Remaining
₹214 Cr
Total
₹680 Cr
Project Approved
Construction / Implementation
Original End Date
13/02/2026
Revised Completion
31/12/2026
Completed
Project is within original budget of ₹686 Cr — no cost escalation recorded.
Expenditure stands at ₹466 Cr, which is 68.6% of the revised project cost.
Remaining budget: ₹214 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.