Roads & HighwaysIPM · Central Project#618368

Improvement and Widening to 2-lane with paved shoulder of road from design Km 36.000 Rangamati to design Km 72.000 Pati Chhari Total length 36.000 Km on Teliamura to Harina section of NH 208 in the state of Tripura on EPC mode under JICA ODA Loan Phase VI Package-3

Ministry of Road Transport & HighwaysTripura
Revised Cost: ₹671 CrUtilization: 27.3%

Original Cost

₹671 Cr

Baseline estimate

On budget

Revised Cost

₹671 Cr

Latest approved cost

Expenditure

₹183 Cr

Spent to date

Utilization

27.3%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹488 Cr

Budget left

Budget Utilization

27.3%
0%25%50%75%100%

Spent

₹183 Cr

Remaining

₹488 Cr

Total

₹671 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

02/09/2026

Revised Completion

31/05/2027

Completed

Project Details

Project Code618368
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateTripura
Data Month2026-08

Financial Summary

Original Cost₹671 Cr
Revised Cost₹671 Cr
Expenditure₹183 Cr
Original End Date02/09/2026
Revised Date31/05/2027

Project Intelligence

Project is within original budget of ₹671 Cr — no cost escalation recorded.

Expenditure stands at ₹183 Cr, which is 27.3% of the revised project cost.

Remaining budget: ₹488 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Improvement and Widening to 2-lane with paved shoulder of road from design Km 36.000 Rangamati to design Km 72.000 Pati Chhari Total length 36.000 Km on Teliamura to Harina section of NH 208 in the state of Tripura on EPC mode under JICA ODA Loan Phase VI Package-3 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹671.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Improvement and Widening to 2-lane with paved shoulder of road from design Km 36"?
Improvement and Widening to 2-lane with paved shoulder of road from design Km 36.000 Rangamati to design Km 72.000 Pati Chhari Total length 36.000 Km on Teliamura to Harina section of NH 208 in the state of Tripura on EPC mode under JICA ODA Loan Phase VI Package-3 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Tripura. Original cost: ₹671 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹671 Cr has not been significantly revised. Expenditure: ₹183 Cr (27.3% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Improvement and Widening to 2-lane with paved shoulder of ro is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618368. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Improvement and Widening to 2-lane with paved shoulder of ro is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.