Improvement and upgradation to two lane with Paved Shoulder configuration from existing km 55.00 to km 90.00 Design length 34.76 of NH-227A near Chhapia Village to near Sikriganj in the State of UP on EPC Mode.
Original Cost
₹307 Cr
Baseline estimate
Revised Cost
₹307 Cr
Latest approved cost
Expenditure
₹126 Cr
Spent to date
Utilization
41.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹181 Cr
Budget left
Budget Utilization
41.0%Spent
₹126 Cr
Remaining
₹181 Cr
Total
₹307 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
02/05/2024
Revised Completion
05/07/2025
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹307 Cr — no cost escalation recorded.
Expenditure stands at ₹126 Cr, which is 41.0% of the revised project cost.
Remaining budget: ₹181 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Improvement and upgradation to two lane with Paved Shoulder configuration from existing km 55.00 to km 90.00 Design length 34.76 of NH-227A near Chhapia Village to near Sikriganj in the State of UP on EPC Mode. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹307.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Improvement and upgradation to two lane with Paved Shoulder configuration from e"?
- Improvement and upgradation to two lane with Paved Shoulder configuration from existing km 55.00 to km 90.00 Design length 34.76 of NH-227A near Chhapia Village to near Sikriganj in the State of UP on EPC Mode. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Uttar Pradesh. Original cost: ₹307 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹307 Cr has not been significantly revised. Expenditure: ₹126 Cr (41.0% of cost). Data as of 2026-05.
- QWhich ministry is responsible for this project?
- Improvement and upgradation to two lane with Paved Shoulder is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618110. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Improvement and upgradation to two lane with Paved Shoulder is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.