Original Cost
₹1004 Cr
Baseline estimate
Revised Cost
₹941 Cr
Latest approved cost
Expenditure
₹385 Cr
Spent to date
Utilization
40.9%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹556 Cr
Budget left
Spent
₹385 Cr
Remaining
₹556 Cr
Total
₹941 Cr
Project Approved
Construction / Implementation
Original End Date
20/12/2025
Revised Completion
31/12/2026
Completed
Project is within original budget of ₹1004 Cr — no cost escalation recorded.
Expenditure stands at ₹385 Cr, which is 40.9% of the revised project cost.
Remaining budget: ₹556 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.