Roads & HighwaysIPM · Central Project#618663

i 4L Vidisha to Hinotiya from km 0.000 to Km 27.000 Vidisha Mehulwa-Talbehat Pkg-I Section of NH- 346 and ii 4L Vidisha to Morikori from Km 39.000 to 59.476 section of NH-146

Ministry of Road Transport & HighwaysMadhya Pradesh
Revised Cost: ₹941 CrUtilization: 46.1%

Original Cost

₹1004 Cr

Baseline estimate

On budget

Revised Cost

₹941 Cr

Latest approved cost

Expenditure

₹434 Cr

Spent to date

Utilization

46.1%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹507 Cr

Budget left

Budget Utilization

46.1%
0%25%50%75%100%

Spent

₹434 Cr

Remaining

₹507 Cr

Total

₹941 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

20/12/2025

Revised Completion

29/12/2026

Completed

Project Details

Project Code618663
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateMadhya Pradesh
Data Month2026-08

Financial Summary

Original Cost₹1004 Cr
Revised Cost₹941 Cr
Expenditure₹434 Cr
Original End Date20/12/2025
Revised Date29/12/2026

Project Intelligence

Project is within original budget of ₹1004 Cr — no cost escalation recorded.

Expenditure stands at ₹434 Cr, which is 46.1% of the revised project cost.

Remaining budget: ₹507 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

i 4L Vidisha to Hinotiya from km 0.000 to Km 27.000 Vidisha Mehulwa-Talbehat Pkg-I Section of NH- 346 and ii 4L Vidisha to Morikori from Km 39.000 to 59.476 section of NH-146 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1004.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "i 4L Vidisha to Hinotiya from km 0.000 to Km 27.000 Vidisha Mehulwa-Talbehat P"?
i 4L Vidisha to Hinotiya from km 0.000 to Km 27.000 Vidisha Mehulwa-Talbehat Pkg-I Section of NH- 346 and ii 4L Vidisha to Morikori from Km 39.000 to 59.476 section of NH-146 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Madhya Pradesh. Original cost: ₹1004 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1004 Cr and has been revised to ₹941 Cr — a cost overrun of -6.3%. Expenditure to date: ₹434 Cr (46.1% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
i 4L Vidisha to Hinotiya from km 0.000 to Km 27.000 Vidisha is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618663. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. i 4L Vidisha to Hinotiya from km 0.000 to Km 27.000 Vidisha is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.