Original Cost
₹160 Cr
Baseline estimate
Revised Cost
₹220 Cr
Latest approved cost
Expenditure
₹142 Cr
Spent to date
Utilization
64.7%
Of revised budget
Cost Status
+37.5%
+₹60 Cr increase
Remaining
₹78 Cr
Budget left
Spent
₹142 Cr
Remaining
₹78 Cr
Total
₹220 Cr
Original Cost
₹160 Cr
Revised Cost
₹220 Cr
Increase
+₹60 Cr
Escalation
+37.5%
Project Approved
Construction / Implementation
Original End Date
30/06/2024
Revised Completion
28/02/2027
Completed
Cost has increased by ₹60 Cr (37.5%) from the original estimate of ₹160 Cr.
Expenditure stands at ₹142 Cr, which is 64.7% of the revised project cost.
Remaining budget: ₹78 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Oil & Gas. Ministry: Ministry of Petroleum & Natural Gas.