Original Cost
₹522 Cr
Baseline estimate
Revised Cost
₹522 Cr
Latest approved cost
Expenditure
₹310 Cr
Spent to date
Utilization
59.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹212 Cr
Budget left
Spent
₹310 Cr
Remaining
₹212 Cr
Total
₹522 Cr
Project Approved
Construction / Implementation
Original End Date
11/07/2026
Revised Completion
11/07/2026
Completed
Project is within original budget of ₹522 Cr — no cost escalation recorded.
Expenditure stands at ₹310 Cr, which is 59.5% of the revised project cost.
Remaining budget: ₹212 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Oil & Gas. Ministry: Ministry of Petroleum & Natural Gas.