Group Gathering Station, Lakwagaon
Original Cost
₹496 Cr
Baseline estimate
Revised Cost
₹496 Cr
Latest approved cost
Expenditure
₹40 Cr
Spent to date
Utilization
8.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹456 Cr
Budget left
Budget Utilization
8.1%Spent
₹40 Cr
Remaining
₹456 Cr
Total
₹496 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
23/10/2027
Revised Completion
23/10/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹496 Cr — no cost escalation recorded.
Expenditure stands at ₹40 Cr, which is 8.1% of the revised project cost.
Remaining budget: ₹456 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Oil & Gas. Ministry: Ministry of Petroleum & Natural Gas.
Group Gathering Station, Lakwagaon is a centrally-funded infrastructure project under Ministry of Petroleum & Natural Gas, in the Oil & Gas sector. The original approved cost is ₹496.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Group Gathering Station, Lakwagaon"?
- Group Gathering Station, Lakwagaon is a centrally-funded infrastructure project under the Ministry of Petroleum & Natural Gas, tracked through the Investment Project Monitoring (IPM) system. Sector: Oil & Gas. State: Assam. Original cost: ₹496 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹496 Cr and has been revised to ₹496 Cr — a cost overrun of -0.1%. Expenditure to date: ₹40 Cr (8.1% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Group Gathering Station, Lakwagaon is under the Ministry of Petroleum & Natural Gas in the Oil & Gas sector. Project code: 619316. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Group Gathering Station, Lakwagaon is one of several Bihar projects tracked under the Oil & Gas sector on the IPM system.