Roads & HighwaysIPM · Central Project +21.0% overrun#619096

Goa / Karnataka Km.93.700 to Kundapur Km.283.30

Ministry of Road Transport & HighwaysKarnataka
Revised Cost: ₹1991 CrUtilization: 92.9%Overrun: +₹346 Cr

Original Cost

₹1645 Cr

Baseline estimate

+21% overrun

Revised Cost

₹1991 Cr

Latest approved cost

Expenditure

₹1850 Cr

Spent to date

Utilization

92.9%

Of revised budget

Escalated

Cost Status

+21.0%

+₹346 Cr increase

Remaining

₹141 Cr

Budget left

Budget Utilization

92.9%
0%25%50%75%100%

Spent

₹1850 Cr

Remaining

₹141 Cr

Total

₹1991 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹1645 Cr

Revised Cost

₹1991 Cr

Increase

+₹346 Cr

Escalation

+21.0%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

28/08/2016

Revised Completion

31/12/2026

Completed

Project Details

Project Code619096
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateKarnataka
Data Month2026-08

Financial Summary

Original Cost₹1645 Cr
Revised Cost₹1991 Cr
Expenditure₹1850 Cr
Original End Date28/08/2016
Revised Date31/12/2026

Project Intelligence

Cost has increased by ₹346 Cr (21.0%) from the original estimate of ₹1645 Cr.

Expenditure stands at ₹1850 Cr, which is 92.9% of the revised project cost.

Remaining budget: ₹141 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Goa / Karnataka Km.93.700 to Kundapur Km.283.30 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1645.00 Cr, later revised to ₹1990.99 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Goa / Karnataka Km.93.700 to Kundapur Km.283.30"?
Goa / Karnataka Km.93.700 to Kundapur Km.283.30 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Karnataka. Original cost: ₹1645 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1645 Cr and has been revised to ₹1991 Cr — a cost overrun of +21%. Expenditure to date: ₹1850 Cr (92.9% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Goa / Karnataka Km.93.700 to Kundapur Km.283.30 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619096. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Goa / Karnataka Km.93.700 to Kundapur Km.283.30 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.