Original Cost
₹1645 Cr
Baseline estimate
Revised Cost
₹1991 Cr
Latest approved cost
Expenditure
₹330 Cr
Spent to date
Utilization
16.6%
Of revised budget
Cost Status
+21.0%
+₹346 Cr increase
Remaining
₹1661 Cr
Budget left
Spent
₹330 Cr
Remaining
₹1661 Cr
Total
₹1991 Cr
Original Cost
₹1645 Cr
Revised Cost
₹1991 Cr
Increase
+₹346 Cr
Escalation
+21.0%
Project Approved
Construction / Implementation
Original End Date
28/08/2016
Revised Completion
31/07/2026
Completed
Cost has increased by ₹346 Cr (21.0%) from the original estimate of ₹1645 Cr.
Expenditure stands at ₹330 Cr, which is 16.6% of the revised project cost.
Remaining budget: ₹1661 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.