Original Cost
₹43.4K Cr
Baseline estimate
Revised Cost
₹43.4K Cr
Latest approved cost
Expenditure
₹5116 Cr
Spent to date
Utilization
11.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹38.3K Cr
Budget left
Spent
₹5116 Cr
Remaining
₹38.3K Cr
Total
₹43.4K Cr
Project Approved
Construction / Implementation
Original End Date
31/05/2028
Revised Completion
31/05/2028
Completed
Mega infrastructure project worth ₹43.4K Cr — among the largest central projects in Madhya Pradesh.
Project is within original budget of ₹43.4K Cr — no cost escalation recorded.
Expenditure stands at ₹5116 Cr, which is 11.8% of the revised project cost.
Remaining budget: ₹38.3K Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Oil & Gas. Ministry: Ministry of Petroleum & Natural Gas.