Oil & GasIPM · Central Project#709798

Ethylene Cracker Project at Bina Refinery including downstream Petrochemical Plants and expansion of Refinery

Ministry of Petroleum & Natural GasMadhya Pradesh
Revised Cost: ₹43.4K CrUtilization: 15.4%

Original Cost

₹43.4K Cr

Baseline estimate

On budget

Revised Cost

₹43.4K Cr

Latest approved cost

Expenditure

₹6689 Cr

Spent to date

Utilization

15.4%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹36.7K Cr

Budget left

Budget Utilization

15.4%
0%25%50%75%100%

Spent

₹6689 Cr

Remaining

₹36.7K Cr

Total

₹43.4K Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/05/2028

Revised Completion

31/05/2028

Completed

Project Details

Project Code709798
SectorOil & Gas
MinistryMinistry of Petroleum & Natural Gas
StateMadhya Pradesh
Data Month2026-08

Financial Summary

Original Cost₹43.4K Cr
Revised Cost₹43.4K Cr
Expenditure₹6689 Cr
Original End Date31/05/2028
Revised Date31/05/2028

Project Intelligence

Mega infrastructure project worth ₹43.4K Cr — among the largest central projects in Madhya Pradesh.

Project is within original budget of ₹43.4K Cr — no cost escalation recorded.

Expenditure stands at ₹6689 Cr, which is 15.4% of the revised project cost.

Remaining budget: ₹36.7K Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Oil & Gas. Ministry: Ministry of Petroleum & Natural Gas.

Ethylene Cracker Project at Bina Refinery including downstream Petrochemical Plants and expansion of Refinery is a centrally-funded infrastructure project under Ministry of Petroleum & Natural Gas, in the Oil & Gas sector. The original approved cost is ₹43367.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Ethylene Cracker Project at Bina Refinery including downstream Petrochemical Pla"?
Ethylene Cracker Project at Bina Refinery including downstream Petrochemical Plants and expansion of Refinery is a centrally-funded infrastructure project under the Ministry of Petroleum & Natural Gas, tracked through the Investment Project Monitoring (IPM) system. Sector: Oil & Gas. State: Madhya Pradesh. Original cost: ₹43367 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹43367 Cr has not been significantly revised. Expenditure: ₹6689 Cr (15.4% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Ethylene Cracker Project at Bina Refinery including downstre is under the Ministry of Petroleum & Natural Gas in the Oil & Gas sector. Project code: 709798. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Ethylene Cracker Project at Bina Refinery including downstre is one of several Bihar projects tracked under the Oil & Gas sector on the IPM system.