Durg-Raipur-Arang Package - 2 from km. 44.50 to km. 92.23 near Khatti Village to near Aurang
Original Cost
₹1959 Cr
Baseline estimate
Revised Cost
₹1562 Cr
Latest approved cost
Expenditure
₹1010 Cr
Spent to date
Utilization
64.6%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹552 Cr
Budget left
Budget Utilization
64.6%Spent
₹1010 Cr
Remaining
₹552 Cr
Total
₹1562 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
28/05/2025
Revised Completion
31/03/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹1959 Cr — no cost escalation recorded.
Expenditure stands at ₹1010 Cr, which is 64.6% of the revised project cost.
Remaining budget: ₹552 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Durg-Raipur-Arang Package - 2 from km. 44.50 to km. 92.23 near Khatti Village to near Aurang is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1959.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Durg-Raipur-Arang Package - 2 from km. 44.50 to km. 92.23 near Khatti Village to"?
- Durg-Raipur-Arang Package - 2 from km. 44.50 to km. 92.23 near Khatti Village to near Aurang is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Chhattisgarh. Original cost: ₹1959 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1959 Cr and has been revised to ₹1562 Cr — a cost overrun of -20.3%. Expenditure to date: ₹1010 Cr (64.6% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Durg-Raipur-Arang Package - 2 from km. 44.50 to km. 92.23 ne is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618590. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Durg-Raipur-Arang Package - 2 from km. 44.50 to km. 92.23 ne is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.