Dharampuri-Lonand from km. 117.00 to 166.40 Pkg-IV on Mohol-Alandi Section
Original Cost
₹1412 Cr
Baseline estimate
Revised Cost
₹1359 Cr
Latest approved cost
Expenditure
₹1474 Cr
Spent to date
Utilization
108.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹0 Cr
Budget left
Budget Utilization
108.5%Spent
₹1474 Cr
Remaining
₹0 Cr
Total
₹1359 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
14/09/2023
Revised Completion
30/09/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹1412 Cr — no cost escalation recorded.
Expenditure stands at ₹1474 Cr, which is 108.5% of the revised project cost.
Remaining budget: ₹0 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Dharampuri-Lonand from km. 117.00 to 166.40 Pkg-IV on Mohol-Alandi Section is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1412.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Dharampuri-Lonand from km. 117.00 to 166.40 Pkg-IV on Mohol-Alandi Section"?
- Dharampuri-Lonand from km. 117.00 to 166.40 Pkg-IV on Mohol-Alandi Section is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Maharashtra. Original cost: ₹1412 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1412 Cr and has been revised to ₹1359 Cr — a cost overrun of -3.8%. Expenditure to date: ₹1474 Cr (108.5% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Dharampuri-Lonand from km. 117.00 to 166.40 Pkg-IV on Mohol- is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619210. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Dharampuri-Lonand from km. 117.00 to 166.40 Pkg-IV on Mohol- is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.