Dhangaon - Borgaon section km 81.000 to km 139.000 [Indore - Edlabad Pkg IV]
Original Cost
₹866 Cr
Baseline estimate
Revised Cost
₹1185 Cr
Latest approved cost
Expenditure
₹747 Cr
Spent to date
Utilization
63.0%
Of revised budget
Cost Status
+36.8%
+₹319 Cr increase
Remaining
₹438 Cr
Budget left
Budget Utilization
63.0%Spent
₹747 Cr
Remaining
₹438 Cr
Total
₹1185 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹866 Cr
Revised Cost
₹1185 Cr
Increase
+₹319 Cr
Escalation
+36.8%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
03/08/2023
Revised Completion
31/10/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹319 Cr (36.8%) from the original estimate of ₹866 Cr.
Expenditure stands at ₹747 Cr, which is 63.0% of the revised project cost.
Remaining budget: ₹438 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Dhangaon - Borgaon section km 81.000 to km 139.000 [Indore - Edlabad Pkg IV] is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹866.00 Cr, later revised to ₹1185.04 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Dhangaon - Borgaon section km 81.000 to km 139.000 [Indore - Edlabad Pkg IV]"?
- Dhangaon - Borgaon section km 81.000 to km 139.000 [Indore - Edlabad Pkg IV] is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Madhya Pradesh. Original cost: ₹866 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹866 Cr and has been revised to ₹1185 Cr — a cost overrun of +36.8%. Expenditure to date: ₹747 Cr (63.0% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Dhangaon - Borgaon section km 81.000 to km 139.000 [Indore - is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619100. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Dhangaon - Borgaon section km 81.000 to km 139.000 [Indore - is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.