Roads & HighwaysIPM · Central Project +36.8% overrun#619100

Dhangaon - Borgaon section km 81.000 to km 139.000 [Indore - Edlabad Pkg IV]

Ministry of Road Transport & HighwaysMadhya Pradesh
Revised Cost: ₹1185 CrUtilization: 63.0%Overrun: +₹319 Cr

Original Cost

₹866 Cr

Baseline estimate

+37% overrun

Revised Cost

₹1185 Cr

Latest approved cost

Expenditure

₹747 Cr

Spent to date

Utilization

63.0%

Of revised budget

Escalated

Cost Status

+36.8%

+₹319 Cr increase

Remaining

₹438 Cr

Budget left

Budget Utilization

63.0%
0%25%50%75%100%

Spent

₹747 Cr

Remaining

₹438 Cr

Total

₹1185 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹866 Cr

Revised Cost

₹1185 Cr

Increase

+₹319 Cr

Escalation

+36.8%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

03/08/2023

Revised Completion

31/10/2026

Completed

Project Details

Project Code619100
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateMadhya Pradesh
Data Month2026-08

Financial Summary

Original Cost₹866 Cr
Revised Cost₹1185 Cr
Expenditure₹747 Cr
Original End Date03/08/2023
Revised Date31/10/2026

Project Intelligence

Cost has increased by ₹319 Cr (36.8%) from the original estimate of ₹866 Cr.

Expenditure stands at ₹747 Cr, which is 63.0% of the revised project cost.

Remaining budget: ₹438 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Dhangaon - Borgaon section km 81.000 to km 139.000 [Indore - Edlabad Pkg IV] is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹866.00 Cr, later revised to ₹1185.04 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Dhangaon - Borgaon section km 81.000 to km 139.000 [Indore - Edlabad Pkg IV]"?
Dhangaon - Borgaon section km 81.000 to km 139.000 [Indore - Edlabad Pkg IV] is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Madhya Pradesh. Original cost: ₹866 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹866 Cr and has been revised to ₹1185 Cr — a cost overrun of +36.8%. Expenditure to date: ₹747 Cr (63.0% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Dhangaon - Borgaon section km 81.000 to km 139.000 [Indore - is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619100. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Dhangaon - Borgaon section km 81.000 to km 139.000 [Indore - is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.