Original Cost
₹866 Cr
Baseline estimate
Revised Cost
₹1185 Cr
Latest approved cost
Expenditure
₹638 Cr
Spent to date
Utilization
53.9%
Of revised budget
Cost Status
+36.8%
+₹319 Cr increase
Remaining
₹547 Cr
Budget left
Spent
₹638 Cr
Remaining
₹547 Cr
Total
₹1185 Cr
Original Cost
₹866 Cr
Revised Cost
₹1185 Cr
Increase
+₹319 Cr
Escalation
+36.8%
Project Approved
Construction / Implementation
Original End Date
03/08/2023
Revised Completion
30/08/2026
Completed
Cost has increased by ₹319 Cr (36.8%) from the original estimate of ₹866 Cr.
Expenditure stands at ₹638 Cr, which is 53.9% of the revised project cost.
Remaining budget: ₹547 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.