Original Cost
₹1031 Cr
Baseline estimate
Revised Cost
₹1125 Cr
Latest approved cost
Expenditure
₹922 Cr
Spent to date
Utilization
82.0%
Of revised budget
Cost Status
+9.1%
+₹94 Cr increase
Remaining
₹203 Cr
Budget left
Spent
₹922 Cr
Remaining
₹203 Cr
Total
₹1125 Cr
Original Cost
₹1031 Cr
Revised Cost
₹1125 Cr
Increase
+₹94 Cr
Escalation
+9.1%
Project Approved
Construction / Implementation
Original End Date
07/11/2022
Revised Completion
30/09/2026
Completed
Cost has increased by ₹94 Cr (9.1%) from the original estimate of ₹1031 Cr.
Expenditure stands at ₹922 Cr, which is 82.0% of the revised project cost.
Remaining budget: ₹203 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Oil & Gas. Ministry: Ministry of Petroleum & Natural Gas.