Dhamra Haldia Pipeline Project
Original Cost
₹1031 Cr
Baseline estimate
Revised Cost
₹1125 Cr
Latest approved cost
Expenditure
₹929 Cr
Spent to date
Utilization
82.6%
Of revised budget
Cost Status
+9.1%
+₹94 Cr increase
Remaining
₹196 Cr
Budget left
Budget Utilization
82.6%Spent
₹929 Cr
Remaining
₹196 Cr
Total
₹1125 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹1031 Cr
Revised Cost
₹1125 Cr
Increase
+₹94 Cr
Escalation
+9.1%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
07/11/2022
Revised Completion
30/09/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹94 Cr (9.1%) from the original estimate of ₹1031 Cr.
Expenditure stands at ₹929 Cr, which is 82.6% of the revised project cost.
Remaining budget: ₹196 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Oil & Gas. Ministry: Ministry of Petroleum & Natural Gas.
Dhamra Haldia Pipeline Project is a centrally-funded infrastructure project under Ministry of Petroleum & Natural Gas, in the Oil & Gas sector. The original approved cost is ₹1031.00 Cr, later revised to ₹1125.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Dhamra Haldia Pipeline Project"?
- Dhamra Haldia Pipeline Project is a centrally-funded infrastructure project under the Ministry of Petroleum & Natural Gas, tracked through the Investment Project Monitoring (IPM) system. Sector: Oil & Gas. State: West Bengal. Original cost: ₹1031 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1031 Cr and has been revised to ₹1125 Cr — a cost overrun of +9.1%. Expenditure to date: ₹929 Cr (82.6% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Dhamra Haldia Pipeline Project is under the Ministry of Petroleum & Natural Gas in the Oil & Gas sector. Project code: 701344. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Dhamra Haldia Pipeline Project is one of several Bihar projects tracked under the Oil & Gas sector on the IPM system.