Development to 4-lane with paved shoulder for the road section Talwandi Sabo-Raman road to refinery Road junction with Bathinda Dabwali Road of NH-254 from existing Km 131.600 to Km 155.650 Design Km 131600 to km 155600 in the State of Punjab. Job No NH-254-PB-2022-23-565
Original Cost
₹547 Cr
Baseline estimate
Revised Cost
₹547 Cr
Latest approved cost
Expenditure
₹383 Cr
Spent to date
Utilization
70.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹164 Cr
Budget left
Budget Utilization
70.0%Spent
₹383 Cr
Remaining
₹164 Cr
Total
₹547 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
05/11/2026
Revised Completion
05/11/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹547 Cr — no cost escalation recorded.
Expenditure stands at ₹383 Cr, which is 70.0% of the revised project cost.
Remaining budget: ₹164 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Development to 4-lane with paved shoulder for the road section Talwandi Sabo-Raman road to refinery Road junction with Bathinda Dabwali Road of NH-254 from existing Km 131.600 to Km 155.650 Design Km 131600 to km 155600 in the State of Punjab. Job No NH-254-PB-2022-23-565 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹547.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Development to 4-lane with paved shoulder for the road section Talwandi Sabo-Ram"?
- Development to 4-lane with paved shoulder for the road section Talwandi Sabo-Raman road to refinery Road junction with Bathinda Dabwali Road of NH-254 from existing Km 131.600 to Km 155.650 Design Km 131600 to km 155600 in the State of Punjab. Job No NH-254-PB-2022-23-565 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Punjab. Original cost: ₹547 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹547 Cr has not been significantly revised. Expenditure: ₹383 Cr (70.0% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Development to 4-lane with paved shoulder for the road secti is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618010. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Development to 4-lane with paved shoulder for the road secti is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.