Original Cost
₹431 Cr
Baseline estimate
Revised Cost
₹431 Cr
Latest approved cost
Expenditure
₹262 Cr
Spent to date
Utilization
60.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹169 Cr
Budget left
Spent
₹262 Cr
Remaining
₹169 Cr
Total
₹431 Cr
Project Approved
Construction / Implementation
Original End Date
21/01/2024
Revised Completion
31/07/2026
Completed
Project is within original budget of ₹431 Cr — no cost escalation recorded.
Expenditure stands at ₹262 Cr, which is 60.8% of the revised project cost.
Remaining budget: ₹169 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Oil & Gas. Ministry: Ministry of Petroleum & Natural Gas.