Development of External Trunk Connectivity and Internal Infrastructure Works at Multi Model Logistics ParkMMLP at Jogighopa in the State of Assam on EPC Mode Package-I Road and Utility Works
Original Cost
₹694 Cr
Baseline estimate
Revised Cost
₹694 Cr
Latest approved cost
Expenditure
₹309 Cr
Spent to date
Utilization
44.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹385 Cr
Budget left
Budget Utilization
44.5%Spent
₹309 Cr
Remaining
₹385 Cr
Total
₹694 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
01/04/2022
Revised Completion
30/09/2024
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹694 Cr — no cost escalation recorded.
Expenditure stands at ₹309 Cr, which is 44.5% of the revised project cost.
Remaining budget: ₹385 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Development of External Trunk Connectivity and Internal Infrastructure Works at Multi Model Logistics ParkMMLP at Jogighopa in the State of Assam on EPC Mode Package-I Road and Utility Works is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹694.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Development of External Trunk Connectivity and Internal Infrastructure Works at "?
- Development of External Trunk Connectivity and Internal Infrastructure Works at Multi Model Logistics ParkMMLP at Jogighopa in the State of Assam on EPC Mode Package-I Road and Utility Works is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Assam. Original cost: ₹694 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹694 Cr has not been significantly revised. Expenditure: ₹309 Cr (44.5% of cost). Data as of 2026-07.
- QWhich ministry is responsible for this project?
- Development of External Trunk Connectivity and Internal Infr is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618455. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Development of External Trunk Connectivity and Internal Infr is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.