Original Cost
₹364 Cr
Baseline estimate
Revised Cost
₹364 Cr
Latest approved cost
Expenditure
₹78 Cr
Spent to date
Utilization
21.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹286 Cr
Budget left
Spent
₹78 Cr
Remaining
₹286 Cr
Total
₹364 Cr
Project Approved
Construction / Implementation
Original End Date
16/01/2027
Revised Completion
16/01/2027
Completed
Project is within original budget of ₹364 Cr — no cost escalation recorded.
Expenditure stands at ₹78 Cr, which is 21.5% of the revised project cost.
Remaining budget: ₹286 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Oil & Gas. Ministry: Ministry of Petroleum & Natural Gas.