Original Cost
₹2715 Cr
Baseline estimate
Revised Cost
₹3717 Cr
Latest approved cost
Expenditure
₹1656 Cr
Spent to date
Utilization
44.6%
Of revised budget
Cost Status
+36.9%
+₹1002 Cr increase
Remaining
₹2061 Cr
Budget left
Spent
₹1656 Cr
Remaining
₹2061 Cr
Total
₹3717 Cr
Original Cost
₹2715 Cr
Revised Cost
₹3717 Cr
Increase
+₹1002 Cr
Escalation
+36.9%
Project Approved
Construction / Implementation
Original End Date
25/09/2024
Revised Completion
31/12/2026
Completed
Cost has increased by ₹1002 Cr (36.9%) from the original estimate of ₹2715 Cr.
Expenditure stands at ₹1656 Cr, which is 44.6% of the revised project cost.
Remaining budget: ₹2061 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.