Original Cost
₹1642 Cr
Baseline estimate
Revised Cost
₹1952 Cr
Latest approved cost
Expenditure
₹1041 Cr
Spent to date
Utilization
53.4%
Of revised budget
Cost Status
+18.9%
+₹310 Cr increase
Remaining
₹910 Cr
Budget left
Spent
₹1041 Cr
Remaining
₹910 Cr
Total
₹1952 Cr
Original Cost
₹1642 Cr
Revised Cost
₹1952 Cr
Increase
+₹310 Cr
Escalation
+18.9%
Project Approved
Construction / Implementation
Original End Date
26/10/2024
Revised Completion
31/10/2027
Completed
Cost has increased by ₹310 Cr (18.9%) from the original estimate of ₹1642 Cr.
Expenditure stands at ₹1041 Cr, which is 53.4% of the revised project cost.
Remaining budget: ₹910 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.