Roads & HighwaysIPM · Central Project +18.9% overrun#619200

Delhi-Amritsar-Katra Expressway Phase-I Spur-III from Junction with Amritsar-Jalandhar road NH-3 near Bhishambarpura to Junction with Amritsar-Anjala road NH-354 near Amritsar Airport [Km 71000 to Km 99000 of Amritsar connectivity]

Ministry of Road Transport & HighwaysPunjab
Revised Cost: ₹1952 CrUtilization: 70.4%Overrun: +₹310 Cr

Original Cost

₹1642 Cr

Baseline estimate

+19% overrun

Revised Cost

₹1952 Cr

Latest approved cost

Expenditure

₹1375 Cr

Spent to date

Utilization

70.4%

Of revised budget

Escalated

Cost Status

+18.9%

+₹310 Cr increase

Remaining

₹577 Cr

Budget left

Budget Utilization

70.4%
0%25%50%75%100%

Spent

₹1375 Cr

Remaining

₹577 Cr

Total

₹1952 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹1642 Cr

Revised Cost

₹1952 Cr

Increase

+₹310 Cr

Escalation

+18.9%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

26/10/2024

Revised Completion

31/12/2027

Completed

Project Details

Project Code619200
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StatePunjab
Data Month2026-08

Financial Summary

Original Cost₹1642 Cr
Revised Cost₹1952 Cr
Expenditure₹1375 Cr
Original End Date26/10/2024
Revised Date31/12/2027

Project Intelligence

Cost has increased by ₹310 Cr (18.9%) from the original estimate of ₹1642 Cr.

Expenditure stands at ₹1375 Cr, which is 70.4% of the revised project cost.

Remaining budget: ₹577 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Delhi-Amritsar-Katra Expressway Phase-I Spur-III from Junction with Amritsar-Jalandhar road NH-3 near Bhishambarpura to Junction with Amritsar-Anjala road NH-354 near Amritsar Airport [Km 71000 to Km 99000 of Amritsar connectivity] is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1642.00 Cr, later revised to ₹1951.70 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Delhi-Amritsar-Katra Expressway Phase-I Spur-III from Junction with Amritsar-Jal"?
Delhi-Amritsar-Katra Expressway Phase-I Spur-III from Junction with Amritsar-Jalandhar road NH-3 near Bhishambarpura to Junction with Amritsar-Anjala road NH-354 near Amritsar Airport [Km 71000 to Km 99000 of Amritsar connectivity] is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Punjab. Original cost: ₹1642 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1642 Cr and has been revised to ₹1952 Cr — a cost overrun of +18.9%. Expenditure to date: ₹1375 Cr (70.4% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Delhi-Amritsar-Katra Expressway Phase-I Spur-III from Juncti is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619200. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Delhi-Amritsar-Katra Expressway Phase-I Spur-III from Juncti is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.