Original Cost
₹2165 Cr
Baseline estimate
Revised Cost
₹1520 Cr
Latest approved cost
Expenditure
₹422 Cr
Spent to date
Utilization
27.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹1097 Cr
Budget left
Spent
₹422 Cr
Remaining
₹1097 Cr
Total
₹1520 Cr
Project Approved
Construction / Implementation
Original End Date
16/04/2026
Revised Completion
10/03/2028
Completed
Project is within original budget of ₹2165 Cr — no cost escalation recorded.
Expenditure stands at ₹422 Cr, which is 27.8% of the revised project cost.
Remaining budget: ₹1097 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.