Roads & HighwaysIPM · Central Project +1.5% overrun#618491

Delhi-Amritsar-Katra Expressway Phase-I Pkg-XI from Junction with Jalandhar - Kapurthala road NH-703A near khojewal village to Junction with Amritsar-Mehta-SriHargobindpur-Tanda road NH-503A near SriHargobindpur Km 319400 to km 362420

Ministry of Road Transport & HighwaysPunjab
Revised Cost: ₹2207 CrUtilization: 62.4%Overrun: +₹32 Cr

Original Cost

₹2175 Cr

Baseline estimate

+2% overrun

Revised Cost

₹2207 Cr

Latest approved cost

Expenditure

₹1377 Cr

Spent to date

Utilization

62.4%

Of revised budget

Escalated

Cost Status

+1.5%

+₹32 Cr increase

Remaining

₹830 Cr

Budget left

Budget Utilization

62.4%
0%25%50%75%100%

Spent

₹1377 Cr

Remaining

₹830 Cr

Total

₹2207 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹2175 Cr

Revised Cost

₹2207 Cr

Increase

+₹32 Cr

Escalation

+1.5%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

14/11/2024

Revised Completion

31/12/2026

Completed

Project Details

Project Code618491
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StatePunjab
Data Month2026-06

Financial Summary

Original Cost₹2175 Cr
Revised Cost₹2207 Cr
Expenditure₹1377 Cr
Original End Date14/11/2024
Revised Date31/12/2026

Project Intelligence

Cost has increased by ₹32 Cr (1.5%) from the original estimate of ₹2175 Cr.

Expenditure stands at ₹1377 Cr, which is 62.4% of the revised project cost.

Remaining budget: ₹830 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Delhi-Amritsar-Katra Expressway Phase-I Pkg-XI from Junction with Jalandhar - Kapurthala road NH-703A near khojewal village to Junction with Amritsar-Mehta-SriHargobindpur-Tanda road NH-503A near SriHargobindpur Km 319400 to km 362420 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹2175.00 Cr, later revised to ₹2206.71 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Delhi-Amritsar-Katra Expressway Phase-I Pkg-XI from Junction with Jalandhar - Ka"?
Delhi-Amritsar-Katra Expressway Phase-I Pkg-XI from Junction with Jalandhar - Kapurthala road NH-703A near khojewal village to Junction with Amritsar-Mehta-SriHargobindpur-Tanda road NH-503A near SriHargobindpur Km 319400 to km 362420 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Punjab. Original cost: ₹2175 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹2175 Cr and has been revised to ₹2207 Cr — a cost overrun of +1.5%. Expenditure to date: ₹1377 Cr (62.4% of revised cost). Data as of 2026-06.
QWhich ministry is responsible for this project?
Delhi-Amritsar-Katra Expressway Phase-I Pkg-XI from Junction is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618491. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Delhi-Amritsar-Katra Expressway Phase-I Pkg-XI from Junction is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.