Original Cost
₹2175 Cr
Baseline estimate
Revised Cost
₹2207 Cr
Latest approved cost
Expenditure
₹941 Cr
Spent to date
Utilization
42.7%
Of revised budget
Cost Status
+1.5%
+₹32 Cr increase
Remaining
₹1266 Cr
Budget left
Spent
₹941 Cr
Remaining
₹1266 Cr
Total
₹2207 Cr
Original Cost
₹2175 Cr
Revised Cost
₹2207 Cr
Increase
+₹32 Cr
Escalation
+1.5%
Project Approved
Construction / Implementation
Original End Date
14/11/2024
Revised Completion
Completed
Cost has increased by ₹32 Cr (1.5%) from the original estimate of ₹2175 Cr.
Expenditure stands at ₹941 Cr, which is 42.7% of the revised project cost.
Remaining budget: ₹1266 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.