Original Cost
₹1896 Cr
Baseline estimate
Revised Cost
₹2035 Cr
Latest approved cost
Expenditure
₹752 Cr
Spent to date
Utilization
37.0%
Of revised budget
Cost Status
+7.3%
+₹139 Cr increase
Remaining
₹1283 Cr
Budget left
Spent
₹752 Cr
Remaining
₹1283 Cr
Total
₹2035 Cr
Original Cost
₹1896 Cr
Revised Cost
₹2035 Cr
Increase
+₹139 Cr
Escalation
+7.3%
Project Approved
Construction / Implementation
Original End Date
13/03/2025
Revised Completion
Completed
Cost has increased by ₹139 Cr (7.3%) from the original estimate of ₹1896 Cr.
Expenditure stands at ₹752 Cr, which is 37.0% of the revised project cost.
Remaining budget: ₹1283 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.