Delhi-Amritsar-Katra Expressway Phase-I Pkg-V from Junction with Ambala-Kaithal-Hissar road NH-152 near Kharak Pandwa village to Junction with Patiala-Samana-Patran road SH-10 near Ghagga village Km 120250 to Km 157920
Original Cost
₹1742 Cr
Baseline estimate
Revised Cost
₹2281 Cr
Latest approved cost
Expenditure
₹1508 Cr
Spent to date
Utilization
66.1%
Of revised budget
Cost Status
+30.9%
+₹539 Cr increase
Remaining
₹773 Cr
Budget left
Budget Utilization
66.1%Spent
₹1508 Cr
Remaining
₹773 Cr
Total
₹2281 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹1742 Cr
Revised Cost
₹2281 Cr
Increase
+₹539 Cr
Escalation
+30.9%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
22/05/2024
Revised Completion
30/09/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹539 Cr (30.9%) from the original estimate of ₹1742 Cr.
Expenditure stands at ₹1508 Cr, which is 66.1% of the revised project cost.
Remaining budget: ₹773 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Delhi-Amritsar-Katra Expressway Phase-I Pkg-V from Junction with Ambala-Kaithal-Hissar road NH-152 near Kharak Pandwa village to Junction with Patiala-Samana-Patran road SH-10 near Ghagga village Km 120250 to Km 157920 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1742.00 Cr, later revised to ₹2281.02 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Delhi-Amritsar-Katra Expressway Phase-I Pkg-V from Junction with Ambala-Kaithal-"?
- Delhi-Amritsar-Katra Expressway Phase-I Pkg-V from Junction with Ambala-Kaithal-Hissar road NH-152 near Kharak Pandwa village to Junction with Patiala-Samana-Patran road SH-10 near Ghagga village Km 120250 to Km 157920 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Punjab. Original cost: ₹1742 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1742 Cr and has been revised to ₹2281 Cr — a cost overrun of +30.9%. Expenditure to date: ₹1508 Cr (66.1% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Delhi-Amritsar-Katra Expressway Phase-I Pkg-V from Junction is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618486. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Delhi-Amritsar-Katra Expressway Phase-I Pkg-V from Junction is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.