Original Cost
₹1742 Cr
Baseline estimate
Revised Cost
₹2281 Cr
Latest approved cost
Expenditure
₹925 Cr
Spent to date
Utilization
40.5%
Of revised budget
Cost Status
+30.9%
+₹539 Cr increase
Remaining
₹1356 Cr
Budget left
Spent
₹925 Cr
Remaining
₹1356 Cr
Total
₹2281 Cr
Original Cost
₹1742 Cr
Revised Cost
₹2281 Cr
Increase
+₹539 Cr
Escalation
+30.9%
Project Approved
Construction / Implementation
Original End Date
22/05/2024
Revised Completion
30/06/2026
Completed
Cost has increased by ₹539 Cr (30.9%) from the original estimate of ₹1742 Cr.
Expenditure stands at ₹925 Cr, which is 40.5% of the revised project cost.
Remaining budget: ₹1356 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.