Original Cost
₹1851 Cr
Baseline estimate
Revised Cost
₹2407 Cr
Latest approved cost
Expenditure
₹1370 Cr
Spent to date
Utilization
56.9%
Of revised budget
Cost Status
+30.0%
+₹556 Cr increase
Remaining
₹1037 Cr
Budget left
Spent
₹1370 Cr
Remaining
₹1037 Cr
Total
₹2407 Cr
Original Cost
₹1851 Cr
Revised Cost
₹2407 Cr
Increase
+₹556 Cr
Escalation
+30.0%
Project Approved
Construction / Implementation
Original End Date
16/07/2024
Revised Completion
31/03/2027
Completed
Cost has increased by ₹556 Cr (30.0%) from the original estimate of ₹1851 Cr.
Expenditure stands at ₹1370 Cr, which is 56.9% of the revised project cost.
Remaining budget: ₹1037 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.