Roads & HighwaysIPM · Central Project +30.0% overrun#618489

Delhi-Amritsar-Katra Expressway Phase-I Pkg-IX from Junction with Ludhiana-Moga road NH-5 near Mullanpur Dakha to Junction with Jalandhar - Moga road NH-703 near Kang Sahibu village Km 260860 to km 303900

Ministry of Road Transport & HighwaysPunjab
Revised Cost: ₹2407 CrUtilization: 80.8%Overrun: +₹556 Cr

Original Cost

₹1851 Cr

Baseline estimate

+30% overrun

Revised Cost

₹2407 Cr

Latest approved cost

Expenditure

₹1944 Cr

Spent to date

Utilization

80.8%

Of revised budget

Escalated

Cost Status

+30.0%

+₹556 Cr increase

Remaining

₹463 Cr

Budget left

Budget Utilization

80.8%
0%25%50%75%100%

Spent

₹1944 Cr

Remaining

₹463 Cr

Total

₹2407 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹1851 Cr

Revised Cost

₹2407 Cr

Increase

+₹556 Cr

Escalation

+30.0%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

16/07/2024

Revised Completion

31/03/2027

Completed

Project Details

Project Code618489
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StatePunjab
Data Month2026-08

Financial Summary

Original Cost₹1851 Cr
Revised Cost₹2407 Cr
Expenditure₹1944 Cr
Original End Date16/07/2024
Revised Date31/03/2027

Project Intelligence

Cost has increased by ₹556 Cr (30.0%) from the original estimate of ₹1851 Cr.

Expenditure stands at ₹1944 Cr, which is 80.8% of the revised project cost.

Remaining budget: ₹463 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Delhi-Amritsar-Katra Expressway Phase-I Pkg-IX from Junction with Ludhiana-Moga road NH-5 near Mullanpur Dakha to Junction with Jalandhar - Moga road NH-703 near Kang Sahibu village Km 260860 to km 303900 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1851.00 Cr, later revised to ₹2407.14 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Delhi-Amritsar-Katra Expressway Phase-I Pkg-IX from Junction with Ludhiana-Moga "?
Delhi-Amritsar-Katra Expressway Phase-I Pkg-IX from Junction with Ludhiana-Moga road NH-5 near Mullanpur Dakha to Junction with Jalandhar - Moga road NH-703 near Kang Sahibu village Km 260860 to km 303900 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Punjab. Original cost: ₹1851 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1851 Cr and has been revised to ₹2407 Cr — a cost overrun of +30%. Expenditure to date: ₹1944 Cr (80.8% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Delhi-Amritsar-Katra Expressway Phase-I Pkg-IX from Junction is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618489. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Delhi-Amritsar-Katra Expressway Phase-I Pkg-IX from Junction is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.