Delhi-Amritsar-Katra Expressway Phase-I Pkg-IX from Junction with Ludhiana-Moga road NH-5 near Mullanpur Dakha to Junction with Jalandhar - Moga road NH-703 near Kang Sahibu village Km 260860 to km 303900
Original Cost
₹1851 Cr
Baseline estimate
Revised Cost
₹2407 Cr
Latest approved cost
Expenditure
₹1944 Cr
Spent to date
Utilization
80.8%
Of revised budget
Cost Status
+30.0%
+₹556 Cr increase
Remaining
₹463 Cr
Budget left
Budget Utilization
80.8%Spent
₹1944 Cr
Remaining
₹463 Cr
Total
₹2407 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹1851 Cr
Revised Cost
₹2407 Cr
Increase
+₹556 Cr
Escalation
+30.0%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
16/07/2024
Revised Completion
31/03/2027
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹556 Cr (30.0%) from the original estimate of ₹1851 Cr.
Expenditure stands at ₹1944 Cr, which is 80.8% of the revised project cost.
Remaining budget: ₹463 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Delhi-Amritsar-Katra Expressway Phase-I Pkg-IX from Junction with Ludhiana-Moga road NH-5 near Mullanpur Dakha to Junction with Jalandhar - Moga road NH-703 near Kang Sahibu village Km 260860 to km 303900 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1851.00 Cr, later revised to ₹2407.14 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Delhi-Amritsar-Katra Expressway Phase-I Pkg-IX from Junction with Ludhiana-Moga "?
- Delhi-Amritsar-Katra Expressway Phase-I Pkg-IX from Junction with Ludhiana-Moga road NH-5 near Mullanpur Dakha to Junction with Jalandhar - Moga road NH-703 near Kang Sahibu village Km 260860 to km 303900 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Punjab. Original cost: ₹1851 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1851 Cr and has been revised to ₹2407 Cr — a cost overrun of +30%. Expenditure to date: ₹1944 Cr (80.8% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Delhi-Amritsar-Katra Expressway Phase-I Pkg-IX from Junction is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618489. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Delhi-Amritsar-Katra Expressway Phase-I Pkg-IX from Junction is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.