Roads & HighwaysIPM · Central Project +20.8% overrun#618485

Delhi-Amritsar-Katra Expressway Phase-I Pkg-IV from Junction with Jind-Karnal road NH-709A near Alewa village to Junction with Ambala-Kaithal-Hissar road NH-152 near Kharak Pandwa village Km 91400 to Km 120250

Ministry of Road Transport & HighwaysHaryana
Revised Cost: ₹1579 CrUtilization: 35.7%Overrun: +₹272 Cr

Original Cost

₹1307 Cr

Baseline estimate

+21% overrun

Revised Cost

₹1579 Cr

Latest approved cost

Expenditure

₹563 Cr

Spent to date

Utilization

35.7%

Of revised budget

Escalated

Cost Status

+20.8%

+₹272 Cr increase

Remaining

₹1015 Cr

Budget left

Budget Utilization

35.7%
0%25%50%75%100%

Spent

₹563 Cr

Remaining

₹1015 Cr

Total

₹1579 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹1307 Cr

Revised Cost

₹1579 Cr

Increase

+₹272 Cr

Escalation

+20.8%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

13/12/2023

Revised Completion

28/03/2024

Completed

Project Details

Project Code618485
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateHaryana
Data Month2026-05

Financial Summary

Original Cost₹1307 Cr
Revised Cost₹1579 Cr
Expenditure₹563 Cr
Original End Date13/12/2023
Revised Date28/03/2024

Project Intelligence

Cost has increased by ₹272 Cr (20.8%) from the original estimate of ₹1307 Cr.

Expenditure stands at ₹563 Cr, which is 35.7% of the revised project cost.

Remaining budget: ₹1015 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Delhi-Amritsar-Katra Expressway Phase-I Pkg-IV from Junction with Jind-Karnal road NH-709A near Alewa village to Junction with Ambala-Kaithal-Hissar road NH-152 near Kharak Pandwa village Km 91400 to Km 120250 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1307.00 Cr, later revised to ₹1578.66 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Delhi-Amritsar-Katra Expressway Phase-I Pkg-IV from Junction with Jind-Karnal ro"?
Delhi-Amritsar-Katra Expressway Phase-I Pkg-IV from Junction with Jind-Karnal road NH-709A near Alewa village to Junction with Ambala-Kaithal-Hissar road NH-152 near Kharak Pandwa village Km 91400 to Km 120250 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Haryana. Original cost: ₹1307 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1307 Cr and has been revised to ₹1579 Cr — a cost overrun of +20.8%. Expenditure to date: ₹563 Cr (35.7% of revised cost). Data as of 2026-05.
QWhich ministry is responsible for this project?
Delhi-Amritsar-Katra Expressway Phase-I Pkg-IV from Junction is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618485. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Delhi-Amritsar-Katra Expressway Phase-I Pkg-IV from Junction is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.