Original Cost
₹1307 Cr
Baseline estimate
Revised Cost
₹1579 Cr
Latest approved cost
Expenditure
₹563 Cr
Spent to date
Utilization
35.7%
Of revised budget
Cost Status
+20.8%
+₹272 Cr increase
Remaining
₹1015 Cr
Budget left
Spent
₹563 Cr
Remaining
₹1015 Cr
Total
₹1579 Cr
Original Cost
₹1307 Cr
Revised Cost
₹1579 Cr
Increase
+₹272 Cr
Escalation
+20.8%
Project Approved
Construction / Implementation
Original End Date
13/12/2023
Revised Completion
28/03/2024
Completed
Cost has increased by ₹272 Cr (20.8%) from the original estimate of ₹1307 Cr.
Expenditure stands at ₹563 Cr, which is 35.7% of the revised project cost.
Remaining budget: ₹1015 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.