Delhi-Amritsar-Katra Expressway Phase-I Pkg-II from Junction with Rohtak-Panipat road NH-709 near Rukhi Paani village to Junction with Jind-Panipat road NH-352A near Gangana village Km 34000 to Km 60800
Original Cost
₹1534 Cr
Baseline estimate
Revised Cost
₹1793 Cr
Latest approved cost
Expenditure
₹1176 Cr
Spent to date
Utilization
65.6%
Of revised budget
Cost Status
+16.9%
+₹259 Cr increase
Remaining
₹616 Cr
Budget left
Budget Utilization
65.6%Spent
₹1176 Cr
Remaining
₹616 Cr
Total
₹1793 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹1534 Cr
Revised Cost
₹1793 Cr
Increase
+₹259 Cr
Escalation
+16.9%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
13/01/2024
Revised Completion
31/07/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹259 Cr (16.9%) from the original estimate of ₹1534 Cr.
Expenditure stands at ₹1176 Cr, which is 65.6% of the revised project cost.
Remaining budget: ₹616 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Delhi-Amritsar-Katra Expressway Phase-I Pkg-II from Junction with Rohtak-Panipat road NH-709 near Rukhi Paani village to Junction with Jind-Panipat road NH-352A near Gangana village Km 34000 to Km 60800 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1534.00 Cr, later revised to ₹1792.53 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Delhi-Amritsar-Katra Expressway Phase-I Pkg-II from Junction with Rohtak-Panipat"?
- Delhi-Amritsar-Katra Expressway Phase-I Pkg-II from Junction with Rohtak-Panipat road NH-709 near Rukhi Paani village to Junction with Jind-Panipat road NH-352A near Gangana village Km 34000 to Km 60800 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Haryana. Original cost: ₹1534 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1534 Cr and has been revised to ₹1793 Cr — a cost overrun of +16.9%. Expenditure to date: ₹1176 Cr (65.6% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Delhi-Amritsar-Katra Expressway Phase-I Pkg-II from Junction is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618483. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Delhi-Amritsar-Katra Expressway Phase-I Pkg-II from Junction is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.