Original Cost
₹1534 Cr
Baseline estimate
Revised Cost
₹1793 Cr
Latest approved cost
Expenditure
₹971 Cr
Spent to date
Utilization
54.2%
Of revised budget
Cost Status
+16.9%
+₹259 Cr increase
Remaining
₹821 Cr
Budget left
Spent
₹971 Cr
Remaining
₹821 Cr
Total
₹1793 Cr
Original Cost
₹1534 Cr
Revised Cost
₹1793 Cr
Increase
+₹259 Cr
Escalation
+16.9%
Project Approved
Construction / Implementation
Original End Date
13/01/2024
Revised Completion
30/06/2026
Completed
Cost has increased by ₹259 Cr (16.9%) from the original estimate of ₹1534 Cr.
Expenditure stands at ₹971 Cr, which is 54.2% of the revised project cost.
Remaining budget: ₹821 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.