Original Cost
₹1455 Cr
Baseline estimate
Revised Cost
₹1806 Cr
Latest approved cost
Expenditure
₹691 Cr
Spent to date
Utilization
38.2%
Of revised budget
Cost Status
+24.1%
+₹351 Cr increase
Remaining
₹1115 Cr
Budget left
Spent
₹691 Cr
Remaining
₹1115 Cr
Total
₹1806 Cr
Original Cost
₹1455 Cr
Revised Cost
₹1806 Cr
Increase
+₹351 Cr
Escalation
+24.1%
Project Approved
Construction / Implementation
Original End Date
24/07/2020
Revised Completion
30/09/2026
Completed
Cost has increased by ₹351 Cr (24.1%) from the original estimate of ₹1455 Cr.
Expenditure stands at ₹691 Cr, which is 38.2% of the revised project cost.
Remaining budget: ₹1115 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.