Roads & HighwaysIPM · Central Project +24.1% overrun#618518

Davanagere - Haveri of NH-48 Old NH-4 from km. 260.00 to km. 338.923

Ministry of Road Transport & HighwaysKarnataka
Revised Cost: ₹1806 CrUtilization: 70.5%Overrun: +₹351 Cr

Original Cost

₹1455 Cr

Baseline estimate

+24% overrun

Revised Cost

₹1806 Cr

Latest approved cost

Expenditure

₹1274 Cr

Spent to date

Utilization

70.5%

Of revised budget

Escalated

Cost Status

+24.1%

+₹351 Cr increase

Remaining

₹532 Cr

Budget left

Budget Utilization

70.5%
0%25%50%75%100%

Spent

₹1274 Cr

Remaining

₹532 Cr

Total

₹1806 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹1455 Cr

Revised Cost

₹1806 Cr

Increase

+₹351 Cr

Escalation

+24.1%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

24/07/2020

Revised Completion

31/12/2026

Completed

Project Details

Project Code618518
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateKarnataka
Data Month2026-08

Financial Summary

Original Cost₹1455 Cr
Revised Cost₹1806 Cr
Expenditure₹1274 Cr
Original End Date24/07/2020
Revised Date31/12/2026

Project Intelligence

Cost has increased by ₹351 Cr (24.1%) from the original estimate of ₹1455 Cr.

Expenditure stands at ₹1274 Cr, which is 70.5% of the revised project cost.

Remaining budget: ₹532 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Davanagere - Haveri of NH-48 Old NH-4 from km. 260.00 to km. 338.923 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1455.00 Cr, later revised to ₹1805.84 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Davanagere - Haveri of NH-48 Old NH-4 from km. 260.00 to km. 338.923"?
Davanagere - Haveri of NH-48 Old NH-4 from km. 260.00 to km. 338.923 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Karnataka. Original cost: ₹1455 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1455 Cr and has been revised to ₹1806 Cr — a cost overrun of +24.1%. Expenditure to date: ₹1274 Cr (70.5% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Davanagere - Haveri of NH-48 Old NH-4 from km. 260.00 to km. is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618518. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Davanagere - Haveri of NH-48 Old NH-4 from km. 260.00 to km. is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.