Oil & GasIPM · Central Project#709837

Creation of Gas Dehydration Facilities, Tripura Asset

Ministry of Petroleum & Natural GasTripura
Revised Cost: ₹132 CrUtilization: 61.8%

Original Cost

₹209 Cr

Baseline estimate

On budget

Revised Cost

₹132 Cr

Latest approved cost

Expenditure

₹81 Cr

Spent to date

Utilization

61.8%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹50 Cr

Budget left

Budget Utilization

61.8%
0%25%50%75%100%

Spent

₹81 Cr

Remaining

₹50 Cr

Total

₹132 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/05/2024

Revised Completion

31/10/2026

Completed

Project Details

Project Code709837
SectorOil & Gas
MinistryMinistry of Petroleum & Natural Gas
StateTripura
Data Month2026-08

Financial Summary

Original Cost₹209 Cr
Revised Cost₹132 Cr
Expenditure₹81 Cr
Original End Date31/05/2024
Revised Date31/10/2026

Project Intelligence

Project is within original budget of ₹209 Cr — no cost escalation recorded.

Expenditure stands at ₹81 Cr, which is 61.8% of the revised project cost.

Remaining budget: ₹50 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Oil & Gas. Ministry: Ministry of Petroleum & Natural Gas.

Creation of Gas Dehydration Facilities, Tripura Asset is a centrally-funded infrastructure project under Ministry of Petroleum & Natural Gas, in the Oil & Gas sector. The original approved cost is ₹209.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Creation of Gas Dehydration Facilities, Tripura Asset"?
Creation of Gas Dehydration Facilities, Tripura Asset is a centrally-funded infrastructure project under the Ministry of Petroleum & Natural Gas, tracked through the Investment Project Monitoring (IPM) system. Sector: Oil & Gas. State: Tripura. Original cost: ₹209 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹209 Cr and has been revised to ₹132 Cr — a cost overrun of -37.1%. Expenditure to date: ₹81 Cr (61.8% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Creation of Gas Dehydration Facilities, Tripura Asset is under the Ministry of Petroleum & Natural Gas in the Oil & Gas sector. Project code: 709837. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Creation of Gas Dehydration Facilities, Tripura Asset is one of several Bihar projects tracked under the Oil & Gas sector on the IPM system.