Original Cost
₹497 Cr
Baseline estimate
Revised Cost
₹497 Cr
Latest approved cost
Expenditure
₹245 Cr
Spent to date
Utilization
49.3%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹252 Cr
Budget left
Spent
₹245 Cr
Remaining
₹252 Cr
Total
₹497 Cr
Project Approved
Construction / Implementation
Original End Date
19/02/2023
Revised Completion
31/03/2026
Completed
Project is within original budget of ₹497 Cr — no cost escalation recorded.
Expenditure stands at ₹245 Cr, which is 49.3% of the revised project cost.
Remaining budget: ₹252 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.