Construction/upgradation to 2-lane with paved shoulder from Design Km 95.55 Bandarkoot to Km. 111.06 Chattroo of 15.52 Km length on Khellani-Kishtwar-Chattroo section on NH-244 in UT of Jammu and Kashmir on EPC Mode Pkg-5
Original Cost
₹497 Cr
Baseline estimate
Revised Cost
₹497 Cr
Latest approved cost
Expenditure
₹271 Cr
Spent to date
Utilization
54.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹226 Cr
Budget left
Budget Utilization
54.5%Spent
₹271 Cr
Remaining
₹226 Cr
Total
₹497 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
19/02/2023
Revised Completion
31/03/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹497 Cr — no cost escalation recorded.
Expenditure stands at ₹271 Cr, which is 54.5% of the revised project cost.
Remaining budget: ₹226 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Construction/upgradation to 2-lane with paved shoulder from Design Km 95.55 Bandarkoot to Km. 111.06 Chattroo of 15.52 Km length on Khellani-Kishtwar-Chattroo section on NH-244 in UT of Jammu and Kashmir on EPC Mode Pkg-5 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹497.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Construction/upgradation to 2-lane with paved shoulder from Design Km 95.55 Band"?
- Construction/upgradation to 2-lane with paved shoulder from Design Km 95.55 Bandarkoot to Km. 111.06 Chattroo of 15.52 Km length on Khellani-Kishtwar-Chattroo section on NH-244 in UT of Jammu and Kashmir on EPC Mode Pkg-5 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Jammu & Kashmir. Original cost: ₹497 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹497 Cr has not been significantly revised. Expenditure: ₹271 Cr (54.5% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Construction/upgradation to 2-lane with paved shoulder from is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619038. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction/upgradation to 2-lane with paved shoulder from is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.