Construction work of 4-laning of Shahganj bypass end to Badi Package-IV of NH-146B from design km 102.000 to design km 142.357 Design length 40.357 km
Original Cost
₹784 Cr
Baseline estimate
Revised Cost
₹837 Cr
Latest approved cost
Expenditure
₹347 Cr
Spent to date
Utilization
41.5%
Of revised budget
Cost Status
+6.7%
+₹53 Cr increase
Remaining
₹489 Cr
Budget left
Budget Utilization
41.5%Spent
₹347 Cr
Remaining
₹489 Cr
Total
₹837 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹784 Cr
Revised Cost
₹837 Cr
Increase
+₹53 Cr
Escalation
+6.7%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
24/03/2027
Revised Completion
24/03/2027
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹53 Cr (6.7%) from the original estimate of ₹784 Cr.
Expenditure stands at ₹347 Cr, which is 41.5% of the revised project cost.
Remaining budget: ₹489 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Construction work of 4-laning of Shahganj bypass end to Badi Package-IV of NH-146B from design km 102.000 to design km 142.357 Design length 40.357 km is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹784.00 Cr, later revised to ₹836.64 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Construction work of 4-laning of Shahganj bypass end to Badi Package-IV of NH-14"?
- Construction work of 4-laning of Shahganj bypass end to Badi Package-IV of NH-146B from design km 102.000 to design km 142.357 Design length 40.357 km is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Madhya Pradesh. Original cost: ₹784 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹784 Cr and has been revised to ₹837 Cr — a cost overrun of +6.7%. Expenditure to date: ₹347 Cr (41.5% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Construction work of 4-laning of Shahganj bypass end to Badi is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618963. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction work of 4-laning of Shahganj bypass end to Badi is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.